15. Commissioning
The following procedures are written for commissioning the system using the
Local Display interface.
15.1. Boot-up Screen
When power is applied to the system, the Local Display will display a iCON
logo screen.
If there is an issue with communication between any components attached to
the thermostat, a critical alert message will appear on the screen. The alert
message will provide detail information concerning the possible cause. Once
the issue is corrected and power is restored to the system the first screen in the
initial commissioning sequence will appear.
Figure 9. Unable to Communicate
15.2. Equipment Discovery
This menu provides access for the installer or service technician to perform
various functions. Advance equipment configurations, notifications, tests,
diagnostics, installation reports and general information about the system.
a.
The first screen to display is the Lennox Logo screen.
b.
The first item to select is the language, on the
Select Language
screen.
The options are English, Français and Español. Select the desired language
and then press the
NEXT
button
c.
The next screen asks if this is a replacement Central Hub?. Is this a
replacement Central Hub? For first time commissioning, select
NO
and
press
continue
.
d.
The Welcome to iCON! Screen is displayed and lists the steps needed to
complete the system setup. Currently there are 3 steps:
•
Equipment Discovery
• Pin Management
•
Local Device Set Up (Optional)
Press
START
to
continue
.
WELCOME
C4
The following steps are needed to complete system setup.
Equipment Discovery
Pin Management
Local Device SetUp (Optional)
WELCOME TO iCON!
START
Figure 10. Welcome Screen
e.
A second screen confirming to begin the search for equipment. Press
Start
to continue.
f.
The equipment discovery screen appears next.
Figure 11. Discovery Screen