A.5 Operation

Module continuously monitors boiler water temperature and 

fi

 res or shuts off burner based on this temperature data.

1. 

When “Call for Heat” occurs, control enables circulator 

and monitors boiler water temperature to determine 

whether thermostat can be satis

fi

 ed without 

fi

 ring 

burners.  

2. 

Control determines burner operation is required, 

module proceeds to start burner (see state codes list) 

and heats water in boiler until setpoint temperature is 

achieved or thermostat is satis

fi

 ed. . 

3. 

Burner is de-activated, ignition module completes heat-

ing cycle, returns to idle and waits for temperature to 

drop again. 

4. 

Circulator is turned on throughout “Call for Heat.”

Table 6 - Operation State Codes

State 

Code 

Number

Defi nition

Explanation

1

Idle

Standby - no call for heat

Circulator

Heat request present. Boiler temperature suf

fi

 ciently high to run circulator 

pump only.

4

Pre-purge

System is purging before ignition trial; includes Pilot Valve circuit diagnostics.

6

Spark

System sparking.  Flame is not present up to 13 seconds

7

Flame stabilization

Flame signal is being established.  Variation in signal is allowed during this 

state, 

fl

 ame must be stable at end of period

8

Running

System is running.  Flame signal must be present.

9

Post-Purge

System is purging at end of call for heat

10

Retry Recycle Delay

Successful ignition was not detected, and delay is called before retry.
Flame signal was lost during state 7 or 8, and delay is called before retry (32 

second delay)

13

Soft lock-out

Soft lockout duration is one hour, may override with manual reset.

14

Hard lock-out

Manual reset is required for hard lockout

15

Wait for limit to close

Possible thermostat call for heat; limit switch is open.

16

Flame out of sequence

Flame signal sensed before trial for ignition.  Appropriate alarm is sent. 

OR

Flame signal sensed out of sequence during post purge.  Appropriate alarm is s

ent.                              OR
Flame signal present when not expected.  Appropriate alarm is sent.

17

Pilot valve diagnostics

Pilot valve circuitry diagnostics during pre-purge.

Current leakage detection

Self check performed at start up, again at beginning of heat cycle, and during 

“Wait for Recovery “ State.

Wait for recovery

Self check performed at start up, again at beginning of heat cycle, and during 

“Wait for Recovery “ State

18

Wait for damper to open

Control has signaled damper/pressure switch 

to  close,  and  is  waiting  for  completion.                                                                                                     

If damper/pressure switch does not close within 60 seconds, control goes to 

State 20.

19

Wait for damper to close

Damper is closed and control waits for damper to open. 

Checked  at  beginning  of  heat  cycle  before  opening  damper.                                                                   

If damper does not open in 60 seconds, control goes to State 21.

20

Wait for damper to open            

(Failed close)

Damper has not opened (end swich not closed) at beginning of heat cycle.   

Alarm message is sent, control is NOT in lockout.

21

Wait for damper to close              

(Failed open)

Damper has not closed despite actuator de-energized.                                 

Alarm message is sent, control is NOT in lockout.

Summary of Contents for GWB8-245E-2

Page 1: ...rds Association for use with Natural and Propane Gases They are constructed and hydrostatically tested for maximum working pressure of 50 psi pounds per square inch in accordance with A S M E American...

Page 2: ...1 DIMENSIONS Table 1 Dimensions BOILER MODEL NUMBER DIMENSIONS INCH FLUE DIAMETER A WIDTH GWB8 245E 2 GWB8 262E 2 7 27 GWB8 280E 2 GWB8 299E 2 7 30 Add 5 to height for vent Damper Figure 1 Dimensions...

Page 3: ...requirements such as intermittent system operation extensive piping systems etc 3 Mbh 1 000 Btuh British Thermal Unit Per Hour Ratings marked Net AHRI Ratings indicate amount of remaining heat input...

Page 4: ...Read this manual and understand all requirements before beginning installation SAFETY SYMBOLS WARNINGS The following defined symbols are used throughout this manual to notify the reader of potential...

Page 5: ...2 Where required by the authority having jurisdiction the installation must conform to the Standard for Controls and Safety Devices for Automatically fired Boilers ANSI ASME CSD 1 3 Boiler series is...

Page 6: ...cted indoor spaces All Outdoor Air Provide permanent opening s communicating directly or by ducts with outdoors A Two Permanent Opening Method Provide opening commencing within 12 inches of top and se...

Page 7: ...of the relief valve outlet over the entire length of discharge line have no intervening shutoff valve between safety relief valve and discharge to atmosphere do not plug or place any obstruction in di...

Page 8: ...e 10 Significant condensation may form in boiler and or venting system if boiler is operated for long period of time with return temperatures of less than 120 F Condensate is corrosive and can cause s...

Page 9: ...9 Figure 5 Chilled Water Piping Figure 4 Typical Hot Water Piping 6 CONNECTING SUPPLY AND RETURN PIPING...

Page 10: ...10 Figure 6 BYPASS PIPING CIRCULATOR ON SUPPLY Figure 7 BYPASS PIPING CIRCULATOR ON RETURN Bypass Piping Required For High Mass Large Water Content Systems 6 CONNECTING SUPPLY AND RETURN PIPING...

Page 11: ...ugged by using plug supplied with vent damper 1 Position furnished vent damper on top of flue outlet collar Fasten damper securely to flue outlet collar with sheet metal screws Verify damper blade has...

Page 12: ...fireplace dampers 4 Place in operation the appliance being inspected Follow the lighting instructions Adjust thermostat so appliance will operate continuously 7 CHIMNEY AND VENT PIPE CONNECTION 5 Tes...

Page 13: ...r indicator points to open position Turn thermostat or controller down again and check damper position indicator returns to closed position Vent Damper Manual Operation Vent damper may be placed in op...

Page 14: ...ld only be made by licensed propane installer Two stage regulation should be used by propane installer Propane gas piping should be checked out by propane installer CHECKING GAS PIPING DANGER Fire Haz...

Page 15: ...y drafts hot or cold pipes sunlight lighting fixtures televisions a fireplace or a chimney 4 Check thermostat operation by raising and lowering thermostat setting as required to start and stop the bur...

Page 16: ...ntegrated High Limit Electronic Ignition Control 240008781 I Inducer is not an option WARNING Modification substitution or elimination of factory equipped supplied or specified components may result i...

Page 17: ...17 11 WIRING DIAGRAMS Figure 13 Integrated High Limit Electronic Ignition Control 240008781...

Page 18: ...18 11 WIRING DIAGRAMS Figure 14 Integrated High Limit Electronic Ignition Control 240008781...

Page 19: ...repeat this process Repeat until you have covered every radiation units in the system ending up at highest unit in system If your units have automatic vents manual venting is unnecessary but it will...

Page 20: ...rol knob slightly and turn clockwise to OFF Do not force WARNING If you do not follow these instructions exactly a fire or explosion may result causing property damage personal injury or loss of life...

Page 21: ...y turning thermostat to lowest setting for one minute then back to normal setting ADJUST PILOT BURNER Pilot flame should surround 3 8 to 1 2 of the pilot sensor See Figure 16 If flame needs adjusting...

Page 22: ...degrees C After setting limit control to limit setting check to see if it shuts off gas supply to burners Turn your thermostat up to call for heat and let boiler run until temperature of water reache...

Page 23: ...T PIPE Venting and piping should be checked at least once a season If vent piping shows any sign of leaking replace immediately WATER SYSTEM If system is to remain out of service during freezing weath...

Page 24: ...inals and wire joints Rollout switch blown Have your service agent check heat exchanged for blockage Replace rollout switch with exact replacement Blocked vent blown Have your service agent check vent...

Page 25: ...nstalled in supply line It will eliminate air from water before it reaches radiators and bleed off this air MAIN AIR VENT FOR DOWN FLOW SYSTEMS OR DIAPHRAGM TYPE EXPANSION TANK Before system is filled...

Page 26: ...ed vent safety switch must be reset manually after switch has cooled off by pushing reset button down Check venting system and chimney for blockage when restoring system to operating condition DO NOT...

Page 27: ...sit Check sensing bulb is fully inserted in well and is not loose Refer to enclosed addendum for wiring instructions when using indirect hot water heater A 3 Adjusting Settings To discourage unauthori...

Page 28: ...retry Flame signal was lost during state 7 or 8 and delay is called before retry 32 second delay 13 Soft lock out Soft lockout duration is one hour may override with manual reset 14 Hard lock out Man...

Page 29: ...and display On retry models wait for retry or reset at thermostat Check for correct installation and wiring before replacing any component Control module cannot be repaired If it malfunctions it must...

Page 30: ...umber of retries exceeded Soft lockout Soft lockout is reset after one hour if alarm reason disappears 63 Soft lockout maximum number of recycles exceeded Soft lockout 64 Soft Lockout electronics fail...

Page 31: ...nnections are clean and tight Replace damaged wire Check for cracked ceramic insulator which can cause short to ground and replace igniter sensor if necessary At gas valve disconnect main valve wire f...

Page 32: ...PRODUCT LITERATURE Lennox Industries Inc Dallas Texas Manufactured by ECR International Inc 2201 Dwyer Avenue Utica NY 13501 web site www ecrinternational com...

Reviews: