Roof penetration:
Install the Taper and Stack
NOTE: It is recommended you install all supplied exhaust stack, as a minimum. Additional stack may be required to
ensure proper draft.
Draft is correct when:
The boil is the same in the syrup pan front-to-back and side-to-side
The fire door is open the flame, sparks, etc. are drawn toward the rear of the arch.
NOTE: When working with stack sections, recognize that the crimped end of the stack
section is the upper / top section.
1.
When installing a roof jack refer to the
2.
If not using a roof jack, make a hole at the point marked on the inside of the roof in
the previous step. The hole should be large enough to allow the stack to be slid into
position and as small as possible to allow for sealing to prevent rain, moisture and
debris from entering the hole.
NOTE: If sealing is done directly around the stack, ensure all governmental
regulations are met for this type of installation.
1.
Place the base taper on the arch stack collar. If you have
difficulty placing the base taper onto the collar, squeeze
the base taper by pressing on the long sides at the base.