Starting up, Maintenance

 

27.06.2018/YACE0068 

Starting up 

 

Note for electric installation on site:  

The devices must be protected with a 16 ampere circuit breaker fitted during 
installation.  

Exception: Devices with 13 ampere UK plugs. 

Firstly, assemble the connecting tube LZM 045 as per diagram (see page 3).  

Attention!

  Do not bend the tube!  

Hold up with open-end wrench SW 14mm. 

Please move the connecting screws for adjustment of the cylindrical chamber always gradually 
(about 2 rotations). Adjust the working chamber as per diagram, and fix it that way it rises 3 mm 
above the bath opening. Refill the bath liquid only up to 15 mm underneath the bath opening and only 
at working temperature and switched-off pump. 

Recommendation for the adjustment of the cylindrical working chamber 

Switch the button for the distribution of the pump flow to 

“ext.” (see diagram Pos. 1). 

 

  Position 

 

 maximum flow rate in the external circuit 

(working chamber). 
The button will be moved anticlockwise. This 
corresponds also to the factory-set up. 

Maintenance 

For cleaning purposes and check-up of the bath liquid, we recommend lifting the front cover with the 
chamber as follows: Remove the connecting flange and release the screws M4. This structural 
component can now be taken out. 

Level  

pump off 

Level  

pump on 

Summary of Contents for RE 212 J

Page 1: ...Lauda Königshofen Germany release 06 2018 c replaces release 11 2016 V02 08 20156 b1 07 04 YACE0068 Phone 49 0 9343 503 0 Fax 49 0 9343 503 222 e mail info lauda de Internet http www lauda de Operating instructions Calibration thermostat RE 212 J RE 312 J Annex to manual RE 212 RE 312 YACE 0060 YACE 0065 ...

Page 2: ......

Page 3: ... immersion depth independent from the volume extension of the bath liquid an extremely good temperature accuracy and distribution of temperature There are pump connectors to connect other external closed circuits but won t be available if the thermostat is used for calibrating Side view Top view EU conformity The device complies with the basic health and safety requirements outline in the Directiv...

Page 4: ... and fix it that way it rises 3 mm above the bath opening Refill the bath liquid only up to 15 mm underneath the bath opening and only at working temperature and switched off pump Recommendation for the adjustment of the cylindrical working chamber Switch the button for the distribution of the pump flow to ext see diagram Pos 1 Position maximum flow rate in the external circuit working chamber The...

Page 5: ... V 60 Hz kW kW kW 2 25 2 25 1 3 2 25 2 25 1 3 Eff Cooling capacity with Ethanol at ambient temperature 20 C 20 C 0 C 20 C 30 C kW kW kW kW 0 30 0 23 0 13 0 04 0 30 0 23 0 13 0 04 Pump type Pressure pump with selection of 5 power stages Pump output max bar 0 4 Discharge pressure max L min 17 Pump connections for tubing mm Nipples dia 13 mm M16 x 1 Bath filling capacity max L 9 12 Bath opening B x T...

Page 6: ...t This equipment generates uses and can radiate radio frequency energy and if not installed and used in accordance with the instruction manual may cause harmful interference to radio communications Operation of this equipment in a residential area is likely to cause harmful interference in which case the user will be required to correct the interference at his own expense Instructions for Class A ...

Reviews: