Opening the Valve for operation 

 

 

If “Press B for gas” is being displayed on the lower half of the LCD it is possible to initiate 

a valve open process as follows. 

 

Press button B 

 

Release button B 

 

Confirm Appliances are off 
by pressing button A 

 

Hold button A until display 
changes to next
 

 

Release button A 

 

Wait for valve to open (~30 
seconds) 

 

Default display – Valve Open 

 

If the High Flow Open Interlock option is active and causes the valve 
to reclose then the “Press B for Gas” display will become available 
again.
 

Repeat 

 

 

 

 

 

Summary of Contents for E6V

Page 1: ...L G Confidential G130 Installation and Commissioning Manual July 2012 ver 01 2012 Landis Gyr Ltd Advanced Metering Infrastructure L G Electronic Smart Ready Gasmeter G130 Installation Manual ...

Page 2: ...d Revision history Issue Date Comments 1 July 2012 First revision of G130 Installation and Commissioning Manual Subject to change without notice Landis Gyr 1 Lysander Drive Northfields Industrial Estate Market Deeping Peterborough PE68FB www Landisgyr com Tel 44 1778 349700 Fax 44 1778 349701 ...

Page 3: ..._________________________5 3 Installation Procedure ___________________________________________________ 6 4 The Service Menu_______________________________________________________ 8 4 1 The Service Menu sequence _________________________________________________8 4 2 Accessing the Service Menu _________________________________________________8 5 Installation_______________________________________ E...

Page 4: ...e applies to the G130 Smart Ready Gas meter E6 residential gas meter 1 2 Purpose This manual contains information required to install and commission the G130 Smart meter 1 3 Target Group The contents of this user manual are intended for technically qualified personnel of energy supply companies responsible for system planning installation and commissioning operation maintenance decommissioning and...

Page 5: ...is user manual are sufficiently qualified strictly observe the safety regulations and the operating information in the individual chapters In particular the owner of the meter bears responsibility for the training of personnel 2 3 Safety Regulations The following safety regulations must be observed at all times This equipment does not contain an Emergency Control Valve Means for shutting off the s...

Page 6: ...r requires no maintenance by the end user The external surfaces may be cleaned if required using a damp or anti static cloth 3 2 The safe removal of the existing meter 1 Isolate the gas supply via the Emergency control valve or other locally defined methodology 2 Record any necessary details such as outgoing meter serial number and the outgoing meter volume index 3 Store outgoing meter for return ...

Page 7: ...uld be followed G130 Valve Status displays 3 5 Display cycle The full display cycle is shown in the diagram below Press A or B to wake the display The index display is then shown Pressing button A will then show the valve status display Another press of button A or a timeout will return to the default display Holding button A whilst in the default display will enter the Rolling Register display se...

Page 8: ...characters are entered pressing button A until the desired character is shown in that position Pressing button B will move to the next character on the right It is possible to roll around back to the beginning if necessary to correct errors Holding button B for more than 3 seconds causes the meter to check the PIN code against the entered one If the PIN code is correct access to the menus is grant...

Page 9: ...Issue 1 9 10 G130 Installation and Commissioning July 2012 ver 01 2012 Landis Gyr Ltd 5 Rolling Register Displays The G130 has a single rolling register which displays the module firmware version ...

Page 10: ...ible to initiate a valve open process as follows Press button B Release button B Confirm Appliances are off by pressing button A Hold button A until display changes to next Release button A Wait for valve to open 30 seconds Default display Valve Open If the High Flow Open Interlock option is active and causes the valve to reclose then the Press B for Gas display will become available again Repeat ...

Reviews: