Transparent panel installation
1. Panel clips 47 are used to secure the transparent panels in place on the greenhouse.
Note: Remove the protective film from both sides of all panels as they are installed.
2. The roof panels 2 and the roof window panel 4 will need to be placed as shown in the picture below. The
bottom edges of these panels need to align above the gutter to direct rain off the greenhouse. The top edges of
these panels need to be placed up under the edge of the crown 33 or the window support beam 15.
3. Place the transparent panels from 1 to 9 in its proper location as shown in the below picture using panel clips
47 to secure all the panels.
Note: When installing the panels 3, 6 and 1, use the frame 35 to connect the panel 3,6 to the panel 1. Insert the
panels into the groove of the frame 35, then install them in the correct place as shown in below pictures.
4. How to attach panel clips, see the picture bellow.
A) Place the two loose ends of the clip into the groove in the frame.
B) Swing the center portion of the clip up against the panel.
C) Two edges of the clip swing under the edge of the panel and the center edge holds the panel in place.
Be careful, panel clip 47 ends may be sharp and may spring back.