6 Commissioning/Start-up/Shutdown
29 of 68
Multitec A SX
6 Commissioning/Start-up/Shutdown
6.1 Commissioning/start-up
6.1.1 Prerequisites for commissioning/start-up
Before commissioning/starting up the pump set, make sure that the following
conditions are met:
▪
The pump set has been properly connected to the electric power supply and is
equipped with all protection devices.
▪
The pump has been primed with the fluid to be handled.
▪
The direction of rotation has been checked.
(
ð
Section 5.8, Page 28)
▪
All auxiliary connections required are connected and operational.
▪
The lubricants have been checked.
▪
After prolonged shutdown of the pump (set), the activities described in
(
ð
Section 6.4, Page 36)
have been carried out.
▪
The quality of the concrete foundation complies with the regulations.
▪
The pump set has been installed and aligned in accordance with the tolerances
specified.
▪
The pipelines have been connected without warping the pump nozzles.
6.1.2 Filling in lubricants
Grease-lubricated bearings
Grease-lubricated bearings have been packed with grease at the factory.
Oil-lubricated bearings
Fill the bearing bracket with lubricating oil.
Oil quality see
(
ð
Section 7.2.3.1.2, Page 42)
Oil quantity see
(
ð
Section 7.2.3.1.3, Page 42)
Filling the constant-level oiler with lubricating oil (oil-lubricated bearings only)
NOTE
If no constant level oiler is provided on the bearing bracket, the oil level can be
read in the middle of the oil level gauge arranged at the side of the bearing
bracket.
CAUTION
Insufficient quantity of lubricating oil in the reservoir of the constant level oiler
Damage to the bearings!
▷
Regularly check the oil level.
▷
Always fill the oil reservoir completely.
▷
Keep the oil reservoir properly filled at all times.