5 Installation at Site
21 of 68
Multitec A SX
5.3.1 Installation on the foundation
1
2
4
3
Fig. 5:
Fitting the shims
1
Bolt-to-bolt clearance
2
Shim
3
Shim for bolt-to-bolt clearance >
800 mm
4
Foundation bolt
ü
The foundation has the required strength and characteristics.
ü
The foundation has been prepared in accordance with the dimensions given in
the outline drawing/general arrangement drawing.
1.
Position the pump set on the foundation and align it with the help of a spirit
level placed on the shaft and discharge nozzle.
Permissible deviation: 0.2 mm/m
2.
Use shims (2) for height compensation, if necessary.
Always fit shims between the baseplate/foundation frame and the foundation
itself; always insert them to the left and right of the foundation bolts (4) and in
close proximity to these bolts.
For a bolt-to-bolt clearance > 800 mm, fit additional shims (3) halfway between
the adjoining holes.
All shims must lie perfectly flush.
3.
Insert the foundation bolts (4) into the holes provided.
4.
Use concrete to set the foundation bolts (4) into the foundation.
5.
Wait until the concrete has set firmly, then align the baseplate.
6.
Tighten the foundation bolts (4) evenly and firmly.
7.
Grout baseplates > 400 mm using low-shrinkage concrete with a standard
particle size and a water/cement ratio ≤ 0.5.
Produce flowability with the help of a solvent.
Perform secondary treatment of the concrete to DIN 1045.
NOTE
For low-noise operation contact the manufacturer to check whether the pump set
can be installed on anti-vibration mounts.
NOTE
Expansion joints can be fitted between pump and suction/discharge line.
Summary of Contents for Multitec A SX
Page 1: ...Sprinkler Pump Multitec A SX Installation Operating Manual ...
Page 67: ......