AIR-SEP
Pressure Maintenance with AIR-SEP
SmartControl
14
KOREX Benelux B.V.
4.4.2
Terminal Plate and AIR-SEP
Smart-Control Controller
Each AIR-SEP
SmartControl controller has a plate, located between the low voltage and the 230V terminals, showing the
terminal designations. All internal connections have already been made in the factory!
View with the fitted Designation Plate
AIR-SEP
SmartControl Controller with Display
5
Initial Commissioning
5.1 System Requirements
(for the legends see
“
2.2 Principle Diagram
”
on pages 7/8)
1.
The AIR-SEP
unit is set pressure-dependent in accordance with your specifications and basically needs no
correction! (for the pre-settings see the label on the electrical cabinet)
2.
The hydraulic connections must be made in accordance with 4.3 (Hydraulic Connections).
3.
The pipe network
–
with closed valves to the AIR-SEP
(3a + 3b and 2b + 2c) - must be charged with at least 1.8
barg pressure.
4.
The supply voltage must be connected in accordance with 4.4 (Electrical Connections).
5.
The safety overflow (2) and the waste water connection of the system separator (1d) must be connected to the sewer
network via a funnel waste trap (2a).
6.
The AIR-SEP
unit must be prefilled with mains water via the filling and draining valve (5) so far until the float in the
water gauge glass (12) is approx. 10cm above the black level switch
(or up to the marker when present).
Fill height at initial
commissioning