KONE ReSolve 200
Installation Instruction
10 (258)
AM-10.65.001
(D) 2013-04-17
© 2009 KONE Corporation
All rights reserved.
One fitter / two fitters working
The table below indicates in which phases of the installation two fitters are required and when
the installation can be undertaking by a single fitter.
This is indicated using symbols in the beginning of the chapters.
= One fitter working
= Two fitters working
Installation phases
one / two fitter(s)
1
Receipt and control of material (two fitters for transportation of
new material)
2
Preparations
OR
3
Installing travelling cables
4
Dismantling old machine room equipment
5
Installing and wiring of machine room equipment
6
Start-up
7
Installing top service limit ramp
8
Installing shaft lighting
9
Removing old elevator shaft equipment
10
Installing hanging wires
11
Installing shaft bundle and positioning magnets
12
Connecting landing door locks and buttons
13
Removing old shaft bundle
14
Installing and wiring of car equipment
15
Installing floor level flags
16
Full speed adjustment / commissioning
17
Removing old equipment