Web: www.kolliasdoors.com
Concluding the guide's suspension process, we continue with its support, wherever it is done
with bolts, plugs or welding. Particular emphasis should be placed on positions near the base where at
least three support points are required (Figure 2). Work is completed by installing support elements per
meter length of the driver.
STEP 3 : Define the distance between vertical guides
We lift the second guide and perform the corresponding actions with the first. In order to safely
define the distance between the guides, it is suggested that the measurements be made between the
inner surfaces of the shaped beams of the guide (Figure 3), both in their upper and lower position.
Figure 3
As in the first guide, special attention is required so that the mounting of the roller shutter’s base
is placed vertically in the building, as shown in (Figure 2).
If screws or plugs are used to support the guides, their application must necessarily be applied
to the girder formed thereon and not to the section through which the roller shutter passes. Length (L)
as well as height (H) is listed on the roll case, as well as on the motors.