Prepare the Receptor and Subfloor (cont.)
Verify that the receptor is level and well supported by the floor. If required, remove the receptor and
place shims under the receptor feet to level the receptor.
When the receptor is leveled, consider whether to use an optional mortar/cement bed to help secure
the unit.
Install a Mortar or Cement Bed (optional)
Remove the receptor from the alcove.
Remove the felt pad if present.
NOTE:
The receptor supports must rest directly on the subfloor.
Build a dam to keep the flooring material clear of the drain area.
NOTE:
Do not use gypsum cement or drywall compound for this application, as they will not provide an
acceptable, durable bond. Use cement or mortar.
NOTE: Do not spread cement or mortar around the receptor feet.
Spread a 2
″
(5.1 cm) layer of cement or mortar on the subfloor.
Remove the dam.
Position a piece of plastic drop cloth material on top of the cement or mortar bed.
Move the receptor into position.
Verify that the receptor is level and resting on all supports.
Clean the receptor to reduce the risk of surface damage.
Position a clean drop cloth or other similar material into the bottom and over the outside edge of
the receptor. Be careful not to scratch the surface of the unit.