10
1128227-A01-D Date: 13/8/2010
I. Test Run the Bath with Airjets
• For information on unit operation, refer to the
• Check all electrical connections, and make sure the
electrical power to the bath with airjets is on.
• Make sure all piping connections in the air harness are secure.
• Verify that the blower motor is secure.
• Temporarily remove the plastic drop cloth or other
protective sheeting from the bath.
• Fill the bath to a level at least 50mm above the top of
the highest airjet.
• Check the drain piping for leaks. Repair any leaks.
•
airjets. Check the air piping for air leaks.
• Stop the bath and drain the water.
• Return the plastic drop cloth or other protectivesheeting
to the bath. Check the drain connections for leakage.
H. Make Electrical Connections
WARNING: Risk of electric shock.
To reduce the
risk of electrical shock, connect the blower motor
to a properly grounded, grounding-type receptacle
protected by Ground-Fault Circuit-Interrupters
(GFCIs). Do not remove the plug grounding pins.
Do not use grounding adapters.
NOTE:
The model number and electrical rating of the blower
is printed on the blower.
• The blower is equipped with a cord and plug. A licensed
electrician must install a dedicated GFCI-protected, 220V, 10A,
grounded outlet. Locate the outlet behind the bath, and within
610mm of the blower motor.
• Plug the blower motor into this outlet.
• Clean the area of all dust and debris.
GFCI-Protected Receptacle
Blower Motor
G. Install the Plumbing
CAUTION: Risk of property damage.
Ensure a
watertight seal on the bath drain.
• Connect the drain to the trap according to the
manufacturer’s instructions.
NOTICE:
An access panel will simplify future maintenance.
• Install the faucet valving according to the faucet
manufacturer’s instructions. Do not install the faucet
trim until instructed. Open the hot and cold water
supplies, and check the supply connections for
leakage.
• Run water into the bath, and check the drain
connections for leakage.
F. Install the Blower
(For Detached Blower Versions Only )
•
Connect the flexible coupling to the blower
using PVC cement
•
Once connected find a suitable installation position for
the blower.
•
Secure the blower firmly using appropriate fixings so
that the blower can not vibrate free when in use
The detached blower can be installed up to 1.5m from
the bath if desired.
Appropriate fixings
through holes in blower
Apply PVC Cement Here
Air blower must be located or fixed so that it cannot
fall into the bath of spa.
•
Summary of Contents for OVE RECT drop in 1709A-GAB-0