![Kohler 15RYG Installation Manual Download Page 24](http://html1.mh-extra.com/html/kohler/15ryg/15ryg_installation-manual_1989786024.webp)
TP-6329 8/07
24
Section 3 Installation Instructions
Carbon monoxide detectors.
Carbon monoxide can
cause severe nausea, fainting, or death.
Install carbon
monoxide detectors on each level of the building. Locate the
detectors to adequately warn the building’s occupants of the
presence of carbon monoxide. Keep the detectors operational
at all times. Periodically test and replace the carbon monoxide
detectors according to the manufacturer’s instructions.
Tools Required:
D
Multimeter (for measuring voltage and current)
D
Frequency meter (may be part of multimeter)
D
Torque wrench
D
Wrenches
D
Screwdrivers
D
Socket wrenches or nut drivers
D
Pliers
D
Safety glasses or goggles
D
Drill with bits and hole saw (outdoor installations)
Installer/Customer-Supplied Items:
D
One 12-volt battery with a minimum rating of 600 cold
cranking amps (CCA) at 0
_
F. Battery kit PA-324553 is
recommended.
D
Gravel or crushed stone (outdoor installations)
D
Concrete mounting pad
D
Cables and conduit
D
Fuel supply line with shutoff valve and pipe sealant
(provided by fuel supplier)
D
Carbon monoxide (CO) detector(s)
D
Exhaust piping (open units)
Required Accessories for Open Units:
D
Silencer: Critical SIEO or engine-mounted
D
Flex exhaust
D
Radiator duct flange
Available Accessories:
D
Air cleaner restriction indicator
D
Battery charger
D
Battery heater
D
Block heater
D
Flexible fuel lines
D
Rain cap
D
Relay kit, includes common fault and auxiliary run
relays
D
Remote digital gauge
D
Rodent guards
D
Skid end caps
3.2 Prepare Site
See Section 1.3 for important factors to consider in
choosing the generator set location.
3.2.1
Indoor Installations, Open Units
Maintain a minimum of 457 mm (18 in.) between the
generator set and any adjacent walls or obstructions to
allow access for maintenance and service.
See
Figure 2-1 for a typical open-unit installation. Prepare
an area for mounting the generator set.
1. Clear all combustible materials from the generator
set location.
2. Refer to the applicable dimension drawing in
Section 7 to find the minimum mounting pad
dimensions.
Lay a concrete pad, including
mounting bolts and stub-ups for the fuel supply and
electrical conduit as shown.
3. Provide air intake and outlet openings as described
in Section 2.2.
3.2.2
Outdoor Installations, Enclosed
Units
Choose a location that is at least 0.9 m (3 ft.) from any
building or structure and near the incoming gas service.
Allow a minimum of 2.4 m (8 ft.) clearance beyond the
exhaust end of the generator set. Plan the installation so
that the exhaust end of the generator set is not directed
toward the building or any openings where exhaust gas
could be drawn into the building.
1. Obtain a building permit and contact your local
utility
companies
to
mark the
locations of
underground pipes and cables.
2. Prepare an area for mounting the generator set.
a. Clear all combustible materials, including
plants and shrubs, building materials, and lawn
furniture, from an area at least 2.4 m (8 ft.)
beyond the exhaust end of the generator set.
b. Spread a 76-mm (3-in.) thick layer of gravel to
support the concrete mounting pad. For the
mounting pad dimensions, see Figure 7-2 for
weather enclosures or Figure 7-6 for sound
enclosures.
c. Lay a 100 mm (4 in.) thick concrete pad on the
gravel layer.
Include mounting bolts and
stub-ups for the fuel supply and electrical
conduit. See Figure 7-2 or Figure 7-6 for the
mounting pad dimensions, mounting bolts, and
stub-up locations.
Summary of Contents for 15RYG
Page 1: ...Commercial Generator Sets Models 15 30RYG TP 6329 8 07c Installation...
Page 32: ...TP 6329 8 07 32 Section 3 Installation Instructions Notes...
Page 42: ...TP 6329 8 07 42 Section 5 Controller Notes...
Page 46: ...TP 6329 8 07 46 Section 6 Generator Reconnection Notes...
Page 60: ...TPMPFP 6329 8 07 60 Notes...
Page 61: ...TPMPFP 6329 8 07 61 Notes...
Page 62: ...TPMPFP 6329 8 07 62 Notes...
Page 63: ......