TP-7045 3/18c
13
Section 3 Cooling System
Section 3 Cooling System
3.1 Ventilation
Engine combustion, generator cooling, and expulsion of
flammable and lethal fumes require ventilation. Provide
ventilation compliant with USCG Regulations governing
sizing of vents and other considerations.
As a rule, size each inlet- and outlet-vent area to a
minimum of 13 sq. cm/30.5 cm (2 sq. in. per ft.) of the
craft’s beam. Should this rule conflict with USCG
Regulations, follow USCG Regulations. For applications
with screened inlets, double the size (4 sq. in. per ft.) of
the hull/deck openings. Extend the vent ducts to bilges to
expel heavier-than-air fumes.
For generator sets mounted in the engine compartment,
increase the air flow to allow for the generator set’s
requirements. Install optional detection devices to
cause alarm, warning, or engine shutdown should
dangerous fumes accumulate in the compartment.
See the generator set specification sheet that shipped
with the generator set for air requirements. The air intake
silencer/cleaner provides combustion air to the engine.
Do not compromise the recommended minimum
clearance of 38 mm (1.5 in.) between a duct opening and
enclosure wall. The engine/generator performance will
decline if you compromise these guidelines.
See
Figure 3-1 for allowable intake restriction.
Note:
ISO 3046 derates apply. See Appendix C.
Model
Allowable
Intake Restriction
,
≤
kPa
(in. H
2
O)
14EKOZD (1 and 3 Phase)
16EKOZD (1 and 3 Phase)
2.4 (9.6)
12EFKOZD (1 and 3 Phase)
13.5EFKOZD (1 and 3 Phase)
1.5 (6.0)
21EKOZD (1 and 3 Phase)
24EKOZD (1 and 3 Phase)
2.2 (8.8)
17EFKOZD (3 Phase)
18EFKOZD (1 Phase)
20.5EFKOZD (1 and 3 Phase)
2.0 (8.0)
32EKOZD (1 and 3 Phase)
4.5 (18)
28EFKOZD (1 and 3 Phase)
3.5 (14)
40EKOZD (1 and 3 Phase)
6 (24)
35EFKOZD (1 and 3 Phase)
4 (16)
Figure 3-1
Combustion Air Intake Restriction
3.2 Cooling System Components
The marine generator set’s cooling system requires the
following components.
3.2.1
Intake Through-Hull Strainer
(Seacock Cover)
Install a screened-intake, through-hull strainer to
prevent entry of foreign objects.
Use perforated,
slotted-hole, or unrestricted-hole design strainers. See
Figure 3-2 for examples of typical strainers. The inner
diameter of the strainer opening must be equal to or
greater than the inner diameter of the water-line hose to
the seawater pump.
1
2
3
4
5
5982--3.1
1. Inside packing
2. Outside packing
3. Seacock cover
4. Direction of vessel movement
5. Typical intake through-hull strainers
Figure 3-2
Seacock Installation, Typical
Do not align the strainer (in relation to the craft’s direction
of travel) with any other through-hull intakes. See
Figure 3-3. Flush mount the recommended through-hull
strainer. Install slotted-hole-design strainers with the
slots parallel to the direction of the vessel’s movement.
Summary of Contents for 12EFKOZD
Page 2: ...TP 7045 3 18c 2...
Page 8: ...TP 7045 3 18c 8 Safety Precautions and Instructions Notes...
Page 12: ...TP 7045 3 18c 12 Section 2 Location Lifting and Mounting Notes...
Page 24: ...TP 7045 3 18c 24 Section 4 Exhaust System Notes...
Page 28: ...TP 7045 3 18c 28 Section 5 Fuel System Notes...
Page 34: ...TP 7045 3 18c 34 Section 6 Electrical System Notes...
Page 50: ...TP 7045 3 18c 50 Section 7 Installation Drawings Notes...
Page 54: ...TP 7045 3 18c 54 Section 8 Reconnection Figure 8 3 Generator Reconnection ADV 5875F U...
Page 81: ...TP 7045 3 18c 81...
Page 82: ...TP 7045 3 18c 82...
Page 83: ...TP 7045 3 18c 83...