1. Secure the Drawer Assembly
CAUTION: Risk of product damage.
Drill the lag bolt pilot holes
in the
ends
of the back rail to provide maximum support and to
prevent flexing of the unit.
NOTE:
The drawer assembly can be aligned as desired with the
vanity top. Take visual impact, leg room, and clearance into account
when determining the height of the drawer assembly.
To properly secure the drawer assembly, 2x6 backing material
must be installed behind the finished wall. Refer to the vanity
installation instructions for site preparation.
Place the drawer assembly in position against the previously
installed vanity and finished wall.
Verify the vanity is level and the back rail is plumb against the
wall.
Using a 1/4
″
drill bit, drill two pilot holes through the ends of
the back rail and the finished wall. Verify the pilot holes are
positioned in the back rail ends and ensure that the lag bolts will
engage the 2x6 backing material.
NOTICE:
Before drilling the pilot holes into the vanity, ensure that
the pilot holes will not damage any of the internal components.
Using a 1/8
″
drill bit, drill two pilot holes through the side of the
drawer assembly and into the vanity.
Pilot Hole
Leveler
Screw
Lag Bolt
Washer
2x6 Bracing
Pilot Hole
Position lag bolts at ends of back rail
and secure into bracing.
Kohler Co.
3
1221226-2-B