01
KINGSPAN ALBION
RELIABLE HOT WATER CYLINDERS
PAGE INSTALL
CONTENT
1
Storage, Handling & Supply Requirements
2
HWA Charter & Benchmark
3
Component
Table
4
Siting the unit
5
General
Installation
7
Discharge
Arrangement
9
Direct
10
Indirect
11
Solar Coil Installation
12
Solar High Limit
13
S-Plan Wiring Schematics
14
Thermostat Wiring Schematics
15
Technical
Specification
17
Commissioning & Servicing
18
Fault
Finding
19
User
Instructions
STORAGE PRIOR TO INSTALLATION
ULTRASTEEL PLUS should be stored in its original packaging in an upright position in an area free from excessive damp.
HANDLING PRODUCT
The ULTRASTEEL PLUS should be carried upright where possible. Assessements of risks for carrying the cylinder should be
conducted. Use more than 1 person for carrying where appropriate. Always follow latest guidelines for lifting techniques, to
avoid injury and damage to the product.
WATER SUPPLY
ULTRASTEEL PLUS operates at 3.0 bar (controlled by the inlet control set) and is capable of delivering over 50 litres per
minute. The high quality inlet control set has been designed to make the most of the flow rates available, however the
performance of any unvented system is only as good as the mains water supply. The maximum possible water demand should
be assessed, taking into consideration that both hot and cold services are supplied simultaneously from the mains.
The water supply should be checked to ensure it can meet these requirements. If necessary, consult the local water company
regarding the likely pressure and flow rate availability.
If measuring the water pressure, note that a high static (no flow) mains pressure is no guarantee of good flow availability. In
a domestic installation 1 bar and 25 l/min. should be regarded as the minimum. The maximum mains pressure that the inlet
control set can accept is 12 bar.
Consideration should be given to upgrading existing 1/2” (15mm) cold mains pipework to a larger size if the recommended
minimum pressure/flow rate is not being achieved.
ELECTRIC SUPPLY
The ULTRASTEEL PLUS requires 240 Volt electrical supply for the immersion elements. The electrical supply to each
immersion heater must be fused at 13A via a double pole isolating switch to BS 60335. The cable must be at least 2.5mm
2
heat
resistant (85°C HOFR) sheathed flex complying to BS EN 50525-1 .
IMPORTANT NOTE TO THE INSTALLER
Read these instructions before commencing installation. Unvented cylinders are a controlled
service as defined in the latest edition of the building regulations and should only be fitted
by a competent person.
The relevant regulations are: England and Wales – Building Regulation G3, Scotland – Technical
Standard P3, N Ireland – Building Regulation Part F
After installation the Benchmark checklist must be completed and left, with these
instructions, with the householder for future reference.
PAGE
HOME OWNER INFORMATION SECTION
H1
Introduction & User Instructions
H2
Servicing
H3
Benchmark
H4
Commissioning Checklist
H5
Service Record
H6-H8
Gaurantee & Gaurantee Card