Emptying intervals:
The light liquid retained in the separator must be removed at the
latest, when the quantity of separated light liquid has reached
80% of the maximum storage capacity.
The sludge in the sludge trap must be removed and disposed of
at the latest, when the separated sludge quantity has reached
half the sludge trap volume.
Attention: Correct functioning is only ensured if the separator is
emptied in good time.
For this reason, a disposal contract should be concluded with a
specialist company. If possible, emptying / disposal work should
be carried out outside business hours.
6. Disposal
21
5. Commissioning
Note and follow the chapter „Safety Instructions“!
5.1 Getting the system ready for operation
Before wastewater containing mineral oil is fed into the separator,
➤
it must be cleaned completely (including inlets and outlets).
Solids and coarse materials must be removed.
➤
The cleaned separator must be filled with cold water
up to the bypass.. (This can be omitted if the tank has been
tested for leaks beforehand and the water was not pumped
out).
➤
Move floater to floating position.
To do this, lift the floater by hand or using a suitable tool until
the water level has reached the outlet edge.
Then check the floating position and movability of the flo-
ater.
5.2 Briefing / handover
The commissioning and briefing are usually carried out by an
installation contractor, but they can also be carried out by a
KESSEL representative on request and for an extra charge.
1. The following persons should be present at the handover:
➤
Person authorised to perform the acceptance on behalf of
the building owner
➤
Specialist company
In addition, we recommend the participation of
➤
Operating staff
➤
Disposal company
2. Preparation of briefing and handover:
➤
Sanitary installations must have been completed.
➤
System filled with water ready for operation.
3. Briefing:
➤
Check the system for tightness, transport and installation
damage and test the pipe connections.
➤
Information about disposal (extraction).
➤
Practical demonstration of the operating possibilities.
4. Handover of the installation and operating instructions.
5. Filling out the commissioning record.
➤
Once the briefing has been completed, the system must
again be made ready for operation.
➤
The commissioning record is provided by your service partner.
Tank system
LW 400
LW 800
LW 1000
Art. no.
99601.002
99601.016
99601.041
measured layer thickness
65 mm
125 mm
180 mm
Sludge (50% fill capacity)
Disposal volume
8.5 l
65 l
180 l
measured layer thickness
95 mm
95 mm
95 mm
Light liquid (80 % fill capacity)
Disposal volume
12 l
48 l
75 l