KEB COMBILINE Service Manual Download Page 5

Service Manual for Medium Frequency Sine-wave Filters

GB-5

2.4.2 

Measurements at the capacitor

Unscrew and mark connections of the capacitor at the terminal strip.

The capacity measurement must be executed as follows:

It is measured between two phases of the delta-connected 

capacitors.

The following capacity value C

Meas 

must result. 

C

Meas

 = 1,5 • C

rated

 ±7,5 %

A failure may occur if one of this three measured values 

differs to the other.The capacitor must be exchanged in 

accordance with chapter 3.

The high-voltage test is made dependent on the insulation tester with the following test 

voltages:

Test voltage phase <-> ground

2,5 kV ac
3,5 kV dc

2.4.3 

Measurement of the insulation strength

The choke can be checked with a high-voltage test on its insulation strength. The test is 

done without capacitor.

Unscrew connections of the capacitor at the terminal strip

The high-voltage test is made dependent on the insulation tester with the following test 

voltages:

Test voltage phase <-> phase

Test voltage phase <-> housing

2,5 kV ac

2,5 kV ac

3,5 kV dc

3,5 kV dc

2.4.4 

Connection of the capacitor lines

The capacitor lines must be connected again in accordance with the marking if the tests are 

without complaint. The terminals must be tightened with the following tightening torque:

Terminal strip

Tightening torque terminal strip

WFF 35

3,0…6,0 Nm

WFF 70

6,0…12 Nm

WFF 120

10…20 Nm

WFF 185

14…31 Nm

WFF 300

25…60 Nm