19
further step.
5.
Turn
on
the
machine's
main
switch.
Note
: If the ‘emergency stop button’ is depressed, it must be released for the machine to run.
6.
After turning the main switch on, wait until the monitor displays “Manual mode” page.
While in this page press the “
” ‘key just underneath the “saw frame” icon as shown in the
following figure. The saw frame (bow) should rise. If the saw frame does not rise, change power
lead connections, by reversing any two of the power leads in the power cord. Make sure you
repeat steps 2 to 6 of this procedure.
Final Inspection Checklist before Operation
After installing the machine, a final inspection should be performed by considering the
following checklist;
Any missing components, guards or panels
Removal of the shipping brace
Lost fasteners and fittings, hoses and conduit
Missing or damaged items
Coolant, oil, or hydraulic leads
Tools and others materials left on saw
Safety measures, general condition and readiness for use
Summary of Contents for KMT 400 KSA
Page 1: ...1 KMT 400 KSA OPERATION MANUAL...
Page 9: ...9 2 Danger Zones on the Machine...
Page 10: ...10 3 Safety Equipments and Assignments...
Page 43: ...43 K1 ELECTRICITY DRAWING...
Page 44: ...44...
Page 45: ...45...
Page 46: ...46...
Page 47: ...47...
Page 48: ...48...
Page 51: ...51 ASSEMBLY OF INFEED TABLE...