RUNGS, HALF AND FULL
Ref. PN 8000 & PN 9000
The Alu rail has two holes at regular intervals to hold the rungs, insert the
bolt along with washer into the rung and tighten it
Step 03 : Installation of Ladder Rung PN9000(01)
27
RECOMMENDED PPE
Forked Lanyard with Energy absorber
Ref: PN 351
Work Positioning Lanyard with Grip Adjuster
Ref: PN 242
Rhino Full Body Harness
Ref: PN 56
Guided Type Fall Arrester System on Flexible
Anchorage Line
Ref: PN 2003
Step 4: Installation of Alu Rail Extension PN (8000 (03))
*
Repeat step 3 to join the Alu rail Extension with the Alu Rail
Intermediate.
*
Select the correct Alu Rail Extension Support depending upon the
type of roof
*
Connect the Alu rail Extension support to the end of the Alurail
Extension using a mounting nut.
*
For trapezoidal roof sheets use blind rivits to install the Alurail
Extension support to the roof,for standing seam fasten the bracket
using nut bolts
27
MOUNTING BRACKET
Ref. PN 8000 & PN 9000
Step 1: Installation of Mounting Nut PN5000(03)
Insert the mounting nut into the alu rail extremity. The first mounting nut
must be at 300mm from the bottom edge and second needs to be
1500mm from the first mounting nut and so on.
The Mounting Brackets can be installed on metal as well as concrete
structure by special fasteners. Chemical fasteners are used to fix the
brackets to the concrete wall and SS fasteners for metal structure. The
shorter end of the bracket is mounted on alu rail by mounting nut and
longer end to the receiving structure by using fasteners
Step 02 : Installation of Alu Rail Extremity PN5000(02) &
Mounting Bracket PN5000(06)
26