Initial Start
7 --- 23
-
During installation of the compressor unit, ensure that a distance of at least 40 ” is
kept between the air intake of the unit and any wall.
Check the oil level in the oil separator tank (see chapter 9.11).
-
Check that the airend rotates in the correct direction (see chapter 7.4).
The ball valve (6.6 and 11.6, see chapter 5.4) must be closed.
The ball valve (20, see chapter 5.4) in the vent line must be open.
Lock the main disconnect in the ”off” position in accordance with ap-
plicable lock out/tag out procedures (example: OSHA CFR 29
§ 1910.147) to ensure the compressor does not restart.
Check all screws on the electrical connections for tightness and
tighten if necessary (carry out this check again after 50 hours of oper-
ation).
Summary of Contents for CSD 75
Page 2: ......
Page 11: ...Technical Specification 1 6...
Page 19: ...Construction and Operation 5 14...
Page 20: ...Construction and Operation 5 15...
Page 58: ...Appendix 11 53 11 Appendix 11 1 Wiring Diagram...
Page 59: ......
Page 60: ......
Page 61: ......
Page 62: ......
Page 63: ......
Page 64: ......
Page 65: ......
Page 66: ......
Page 67: ......
Page 68: ......
Page 69: ......
Page 70: ......
Page 71: ......
Page 72: ......
Page 73: ......
Page 74: ......
Page 75: ......
Page 76: ......