4 For Professional Technical Support call 1-844-242-2475
SPECIFICATIONS
NOTICE
:
Read this Owner’s Manual for installation, operation, and safety information.
INSTALLATION
NOTICE:
Install pump on a hard, level surface (cement, asphalt, etc.). Never place pump directly on earth, clay or
gravel surfaces.
Piping
– Effluent Applications (3/4” or Less Solids)
Piping must be 1-1/2
” minimum to carry volume of pump discharge. Check local codes to determine if a check valve is
required in your system. In cold climates, check valves are not used to prevent effluent from freezing in piping.
If using as a sump pump, a check valve is recommended.
Piping
– Sewage Applications (2”or Less Solids)
In any case, piping must not be smaller than pump discharge. When installed in a sewage system, pipe must be capable
of handling semi-solids of at least 2
” (5.1 cm) diameter. The rate of flow in the discharge pipe must keep any solids
present in suspension in the fluid. To meet minimum flow requirements,
the minimum pipe size is 2”.
Use a 2
” (5.1 cm) swing check valve in pump discharge to prevent backflow of liquid into sump basin. Check valve
should be a free flow valve that will easily pass solids.
NOTICE:
For best performance of check valve when handling solids, do not install it with discharge angled more than
45° above the horizontal. Do not install check valve in a vertical position as solids may settle in valve and prevent
opening on start up.
Drill a 1/8
” (3.2mm) hole in discharge pipe about 1”-2” (2.5 - 5.1cm) above pump discharge connection (but below check
valve) to prevent air locking the pump.
PIPE QUICK CONNECTION:
Insert rigid plastic pipe into the quick connector.
Hand tighten the knurling nut of the quick connector as tight as possible.
Power supply
SWW05002TPK/
SWW05002VPK:115V, 60 HZ., 15 Amp Circuit
SWW07503TPK/SWW05001TPK/SWW05001VPK/SWW07501TPK/SWW07501VPK:
115V, 60 HZ., 20 Amp Circuit
Liquid temp. range
32-131°F (0-55°C)
Discharge size
2” FNPT
Sump basin
Minimum 22 in. (559 mm) diameter, 30 in. (760 mm) depth