In Venetian blind operation, each pair of adjacent load outputs forms a blind output. In each
case the left-hand load output
A1, A3, ...
is intended for the upwards direction, and the
right-hand load output
A2, A4, ...
for the downwards direction.
CAUTION!
Overloading the device leads to excessive heating.
Damage to the device and the connected cables may result.
Do not exceed the maximum current carrying capacity.
o
Connect loads as shown in the wiring example (figure 4).
Figure 4: Wiring example for mains voltage and loads
Connecting a control section
Operation take place using the devices listed under Accessories.
In case of operation with sensor modules (17) or push-button modules (17) do not connect any
other control sections such as push-buttons 24 V (16), push-button modules 24 V (16) and unlit
installation buttons (18), to the relay station.
Observe technical data, especially the maximum number of sensor modules and push-button
modules, load capacity of the activation outputs and switching inputs.
o
Connect control sections according to wiring examples (figure 5), (figure 6) or (figure 7).