MCHZ/EN (0912) 4.2
Commissioning
21
MCHZ
4 Commissioning
4.1
Inspection of the pump
• Construction with stuffing box packing: check whether the gland nuts have not been
over tightened. If necessary, loosen these nuts and tighten them again by hand.
• Check whether the pump shaft turns freely. Do this by turning the shaft end at the
coupling a few times by hand.
4.2
Inspection of the motor
Pump driven by an electric motor:
• Check whether the fuses have been mounted.
4.3
Preparing the pump unit for commissioning
Proceed as follows, both when the unit is put into operation for the first time and after the
pump has been overhauled:
1 Fully open the stop valve in the suction pipe. Close the delivery stop valve.
2 Fill the pump and the suction pipe with the liquid to be pumped.
3 Turn the pump shaft a few times by hand and add more liquid, if necessary.
4.4
Checking the sense of rotation
Beware of possible non-screened rotating parts, when checking the sense of
rotation!
1 The sense of rotation of the pump is indicated by an arrow. Check whether the sense
of rotation of the motor corresponds with that of the pump.
2 Let the motor run for only a short time and check the sense of rotation.
3 If the sense of rotation is
not
correct, alter the sense of rotation. See the instructions
in the user manual belonging to the electric motor.
4 Fit the guard.
Summary of Contents for MCHC
Page 5: ...4 MCHZ EN 0912 4 2 ...
Page 48: ...MCHZ EN 0912 4 2 Dimensions 47 MCHZ 8 Dimensions ...
Page 59: ...58 Dimensions MCHZ EN 0912 4 2 ...
Page 61: ...60 Parts MCHZ EN 0808 4 1 9 3 MCHZ 12 5 14a b 16 Figure 27 MCHZ 12 5 14a b 16 ...
Page 63: ...62 Parts MCHZ EN 0808 4 1 9 4 MCHZS 12 5 14a b 16 Figure 28 MCHZS 12 5 14a b 16 ...
Page 70: ...MCHZ EN 0808 4 1 Parts 69 MCHZ 9 7 MCHZ 20a b Figure 31 MCHZ 20 a b ...
Page 72: ...MCHZ EN 0808 4 1 Parts 71 MCHZ 9 8 MCHZS 20a b Figure 32 MCHZS 20 a b ...
Page 81: ...80 Technical data MCHZ EN 0912 4 2 ...
Page 85: ...84 ORDFORM 0804 3 1 EN ...