SECTION V: ELECTRICAL POWER

ELECTRICAL POWER CONNECTIONS

Field wiring to the unit must be grounded. Electric wires that are field
installed shall conform to the temperature limitation for 63°F (35°C) rise
wire when installed in accordance with instructions. Refer to Table 6 in
these instructions for specific furnace electrical data.

Annual Fuel Utilization Efficiency (AFUE) numbers are determined in accordance with DOE Test procedures.
Wire size and over current protection must comply with the National Electrical Code (NFPA-70-latest edition) and all local codes.
The furnace shall be installed so that the electrical components are protected from water.

SUPPLY VOLTAGE CONNECTIONS

1. Provide a power supply separate from all other circuits. Install over-

current protection and disconnect switch per local/national electrical
codes. The switch should be close to the unit for convenience in
servicing. With the disconnect or fused switch in the OFF position,
check all wiring against the unit wiring label. Refer to the wiring dia-
gram in this instruction.

2. Remove the wiring box cover screws. Route all power wiring

through a conduit connector or other proper bushing that is field
installed into the unit opening and the junction box. In the junction
box there is a black wire, a white wire and a green ground screw.
Connect the power supply as shown on the unit’s wiring label
located on the inside of the blower compartment door, or the wiring
schematic in this section. Connect the black wire to L1 (hot) from
the power supply. Connect the white wire to neutral. Connect the
ground wire (installer-supplied) to the green (equipment ground)
screw. An alternate wiring method is to use a field-provided 2” (5.1
cm) x 4” (10.2 cm) box and cover on the outside of the furnace.
Route the furnace leads into the box using a protective bushing
where the wires pass through the furnace panel. After making the
wiring connections, replace the wiring box cover and screws. Refer
to Figure 17.

3. The furnace's control system requires correct polarity of the power

supply and a proper ground connection. Refer to Figure 17.

LOW VOLTAGE CONTROL WIRING CONNECTIONS

Install the field-supplied thermostat by following the instructions that
come with the thermostat. With the thermostat set in the OFF position
and the main electrical source disconnected, connect the thermostat
wiring from the wiring connections on the thermostat to the terminal
board on the ignition module, as shown in Figures 18 or 19. Electronic
thermostats may require the common wire to be connected. Apply
strain relief to thermostat wires passing through cabinet. If air condition-
ing equipment is installed, use thermostat wiring to connect the Y and C
terminals on the furnace control board to the proper wires on the con-
densing unit (unit outside). 

The 24-volt, 40 VA transformer is sized for the furnace components
only, and should not be connected to power auxiliary devices such as
humidifiers, air cleaners, etc. The transformer may provide power for an
air conditioning unit contactor.

Use copper conductors only.

Table 6: 

Ratings & Physical / Electrical Data

Input

Output

Nominal

Airflow

AFUE

%

Air Temp. Rise

Max. Outlet

Air Temp

Blower

Blower 

Size

Max 

Over-Current 

Protect

Total Unit

Amps

Min. wire Size 

(awg) @ 75 ft 

one way

MBH kW MBH kW CFM m

3

/min

°F

°C

°F

°C

HP

Amps

40

11.7

38

11.1 1000

28.3

95.5

30-60

17-33

180

82.2

1/2

6.8

11x8

15

9.5

14

60 17.6

57

16.7 1200

34.0

95.5

30-60

17-33

180

82.2

1/2

6.8

11x8

15

9.5

14

80 23.4

76

22.3 1200

34.0

95.5

40-70

22-39

170

76.7

1/2

6.8

11x8

15

9.5

14

80 23.4

76

22.3 1600

45.3

95.5

35-65

19-36

165

73.9

1/2

6.8

11x10

15

9.5

14

100 29.3

95

27.8 1600

45.3

95.5

40-70

22-39

170

76.7

1/2

6.8

11x10

15

9.5

14

100 29.3

95

27.8 2000

56.6

95.5

35-65

19-36

165

73.9

3/4

8.4

11x11

15

10.9

14

120 35.1 114 33.4 2000

56.6

95.5

45-75

25-42

175

79.4

3/4

8.4

11x11

15

10.9

14

 FIGURE 17:  

Electrical Wiring

Electrical Entry

Junction
Box

L1-Hot

Neutral

Connect ground
lead to screw

BLK

WHT

The power connection leads and wiring box may be relocated to the
opposite side of the furnace. Remove the screws and cut wire tie
holding excess wiring. Reposition on the opposite side of the furnace
and fasten using holes provided.

Set the heat anticipator in the room thermostat to 0.4 amps. Setting it
lower will cause short cycles. Setting it higher will cause the room
temperature to exceed the set points.

Some electronic thermostats do not have adjustable heat anticipa-
tors. They should be set to six cycles per hour. Follow the thermostat
manufacturer's instructions.

Summary of Contents for TM9X

Page 1: ...n 26 Downward Venting 26 Direct Vent Air Intake Connection and Vent Connection 26 Combustion Airflow Path Through The Furnace Casing 27 Ambient Combustion Air 28 Attic and Crawl Space Combustion Air T...

Page 2: ...ition input rate temperature rise and venting according to the manufacturer s instructions 10 When installed in a non HUD Approved Modular Home or building constructed on site combustion air shall not...

Page 3: ...ng jurisdiction In the United States and Canada follow all codes and standards for the following using the latest edition available STEP 1 Safety US National Fuel Gas Code NFGC NFPA 54 ANSI Z223 1 and...

Page 4: ...on FOR FURNACES INSTALLED IN THE COMMON WEALTH OF MASSACHUSETTS ONLY For all side wall horizontally vented gas fueled equipment installed in every dwelling building or structure used in whole or in pa...

Page 5: ...r This access cover shall be attached in such a manner as to prevent leaks DUCT FLANGES Four flanges are provided to attach ductwork to the furnace These flanges are rotated down for shipment In order...

Page 6: ...tal left hand applications no conversion is required to an MC coil when used with a downflow horizontal furnace A mounting plate supplied with every coil should always be installed on the side desig n...

Page 7: ...n a flat solid surface this bottom panel will provide an adequate seal to prevent air leakage through the unused bottom opening However if the furnace is to be installed on a surface that is uneven or...

Page 8: ...e one support located approximately in the center of the furnace near the blower shelf and the third support should be at the return end of the fur nace Maintain a 6 15 2 cm minimum clearance between...

Page 9: ...rain Optional Return Air Cutout Either side 29 5 For Cladded door add appoximately an additional 75 C SUPPLY END 56 56 20 B 3 23 8 56 Combustion Air Inlet Vent Outlet RETURN END B 24 25 Table 3 Cabine...

Page 10: ...r that has previously serviced another gas appliance Some utility companies or local codes require pipe sizes larger than the minimum sizes listed in these instructions and in the codes The furnace ra...

Page 11: ...Gas Piping Upflow Configuration Downflow Configuration Horizontal Configuration External Manual Shut off Valve External Manual Shut off Valve External Manual Shut off Valve To Gas Supply To Gas Suppl...

Page 12: ...xide personal injury property damage a fire hazard and or death High altitude and propane LP conversions are required in order for the appliance to satisfactory meet the application An authorized dist...

Page 13: ...Install the field supplied thermostat by following the instructions that come with the thermostat With the thermostat set in the OFF position and the main electrical source disconnected connect the th...

Page 14: ...Single Stage Furnace STD ECM Single Stage Air Conditoner STD ECM Y Compressor 24 Volt Common C 24 Volt Common Compressor Contactor R 24 Volt Hot Y Y2 Second or Full Stage Compressor FIGURE 19 Typical...

Page 15: ...rnace to not operate No hose clamps are needed for connecting to the condensate pan The condensate will flow to the drain better if an open stand pipe is installed in the drain line See Figure 20 If e...

Page 16: ...ake coupling the drain opening in the vent drain must not be plugged If the intake drain is used the bird screen cannot be installed This is only approved for upflow and horizontal applications when t...

Page 17: ...f so that no sagging loops will collect and hold condensate which will cause the furnace to not operate Shorten pressure switch hose Re route and shorten pressure switch hose Shorten rain gutter hose...

Page 18: ...itch hose to this position NOTE May require the longer hose that is provided with wider cabinets Move condensate drain hose to this position May exit either side of the cabinet Move rain gutter hose t...

Page 19: ...ose to this position NOTE May require the longer hose that is provided with wider cabinets Change condensate drain connection to the 90 fitting provided Move condensate drain hose to this position Mov...

Page 20: ...tting provided Move condensate drain hose to this position Move rain gutter hose to this position Change condensate drain connection to the 90 fitting provided Move condensate drain hose to this posit...

Page 21: ...o be used any joint where ABS pipe is joined to PVC pipe must be glued with cement that is approved for use with BOTH materials Metallic materials must not be used for venting or air intake 5 If a fle...

Page 22: ...3 55 60 000 4 140 60 000 4 120 80 000 2 50 80 000 2 20 80 000 3 75 80 000 3 55 80 000 4 140 80 000 4 120 100 000 2 15 100 000 2 NA 100 000 3 75 100 000 3 55 100 000 4 140 100 000 4 120 120 000 3 75 1...

Page 23: ...IGURE 25 Elbow Dimensions TABLE 9 Elbow Dimensions Elbow A Dimension Illustrated in Figure 25 2 Standard 2 5 16 3 Standard 3 1 16 2 Sweep 3 1 4 3 Sweep 4 1 16 TABLE 10 Equivalent Length of Fittings Fi...

Page 24: ...quirements of the gas supplier 12 30 5 cm or in accordance with local installation codes and the requirements of the gas supplier F Clearance to outside corner 12 30 5 cm or in accord ance with local...

Page 25: ...ch furnace must have a separate vent pipe Under NO circumstances can the two vent pipes be tied together The combustion air side of the two pipe configuration shown in Figures 28 and 29 can be install...

Page 26: ...ns Refer to Ambient Combustion Air Supply for proper installa tion Refer to Figures 34 and 35 3 VENTILATED COMBUSTION AIR Combustion air is supplied through a PVC or ABS pipe that is connected to the...

Page 27: ...adjustable louvers are not permitted for use 4 A automatically operated damper or automatically adjustable lou vers shall be interlocked so that the main burner cannot operate unless either the dampe...

Page 28: ...322 cm2 per 0 879 kW of the total input rating of all equipment located in the enclosure b Not less than the sum of all vent connectors in the confined space 3 The duct shall be least the same cross...

Page 29: ...clothes dryers and TURN ON any exhaust fans such as range hoods and bathroom exhausts so they shall operate at maximum speed Open the fireplace dampers Do not operate a summer exhaust fan 4 Follow th...

Page 30: ...eter 1 Turn off all other gas appliances and pilots 2 Run furnace for a minimum of 3 minutes in heating operation 3 Measure time in sec for gas meter to complete 1 revolution and note reading The 2 cu...

Page 31: ...300 750 78 46 92 231 25 144 288 720 80 45 90 225 26 138 277 692 82 44 88 220 27 133 267 667 84 43 86 214 28 129 257 643 86 42 84 209 29 124 248 621 88 41 82 205 30 120 240 600 90 40 80 200 31 116 232...

Page 32: ...ng gas valve regulator screw for the appropriate gas per the following 4 After the manifold pressure has been adjusted re calculate the fur nace input to make sure you have not exceeded the specified...

Page 33: ...n control The fan on delay is fixed at 30 seconds The fan off delay has 4 settings 60 90 120 and 180 seconds The fan off delay is factory set to 120 sec onds The fan off setting must be long enough to...

Page 34: ...1203 1182 1150 1125 1095 1064 1031 980 Medium 1076 1059 1029 1007 973 946 908 883 843 800 Medium Low 988 967 936 903 875 838 806 765 737 685 Low 798 769 727 695 650 619 574 517 485 443 TM9X080B12MP11...

Page 35: ...off and a retry operation begins Also if the flame is lost for 2 seconds during the 10 second stabilization period the gas valve is shut off and a retry operation begins During a retry operation the...

Page 36: ...rmer wires Both heating and cooling operations will be affected Check polarity at furnace and branch Check furnace grounding Check that flame probe is not shorted to chassis The furnace will not start...

Page 37: ...ING FERRULE 3 req d GASKET FOAM Door 1 5 ft req d GROMMET 3 req d HARNESS WIRING HOSE CONDENSATE HOSE RAIN GUTTER KNOB QUARTER TURN 4 req d MOTOR MOUNT ORIFICE BURNER Natural 45 PAN CONDENSATE PLUG SE...

Page 38: ...AVEC LE SERVICE 1042427 UWD A 0413 Fault Code Retrieval To retrieve fault codes push and release ERROR button on control board The LED will flash the last five error codes beginning with the most rece...

Page 39: ...correct black is L1 hot white is N neutral Ground wire is connected Line voltage value to furnace volts AC Low voltage value between R and C on furnace control board volts AC Thermostat Type Other Sy...

Page 40: ...ot Selectable Explain the importance of regular filter replacement and equipment maintenance Gas Side Air Side System External Static Pressure Owner Education Additional Job Detail Supply static befor...