CONTROL CIRCUIT FUSE

A 3-amp fuse is provided on the control circuit board to protect the 24-
volt transformer from overload caused by control circuit wiring errors.
This is an ATO 3, automotive type fuse and is located on the control
board.

BLOWER DOOR SAFETY SWITCH

This unit is equipped with an electrical interlock switch mounted in the
burner compartment. This switch interrupts all power at the unit when
the panel covering the blower compartment is removed.

Electrical supply to this unit is dependent upon the panel that covers the
blower compartment being in place and properly positioned.

ROLLOUT SWITCH CONTROLS

These controls are mounted on the burner assembly. If the temperature
in the area surrounding the burner exceeds its set point, the gas valve
is de-energized. The operation of this control indicates a malfunction in
the combustion air blower, heat exchanger or a blocked vent pipe con-
nection. Corrective action is required. These are manual reset controls
that must be reset before operation can continue.

PRESSURE SWITCHES

This furnace is supplied with a pressure switch, which monitors the flow
through the combustion air/vent piping system. This switch de-ener-
gizes the gas valve if any of the following conditions are present.

1.

Blockage of vent piping or terminal.

2.

Failure of combustion air blower motor.

LIMIT CONTROLS

There is a high temperature limit control located on the furnace vesti-
bule panel near the gas valve. This is an automatic reset control that
provides over temperature protection due to reduced airflow. This may
be caused by:

1.

A dirty filter.

2.

If the indoor fan motor should fail.

3.

Too many supply or return registers closed or blocked off.

The control module will lockout if the limit trips 5 consecutive times. If
this occurs, control will reset & try ignition again after 1 hour. 

SEQUENCE OF OPERATION

The following describes the sequence of operation of the furnace. Refer
to Owners Manual for component location.

Continuous Blower

Cooling/heating thermostats have a fan switch that has an ON and
AUTO position. In the ON position the thermostat circuit is completed
between terminals R and G. The motor will operate continuously on the
speed tap wire that is connected to the “HI COOL” cooling terminal on
the control board. To obtain a constant air circulation at lower flow rate,
change the high-speed wire to either the medium speed wire or the low
speed wire.

Intermittent Blower - Cooling

Cooling/heating thermostats have a fan switch that has an ON and
AUTO position. In the AUTO position the thermostat circuit is completed
between terminals R and G when there is a call for cooling. The motor
will operate on the speed tap wire that is connected to the “HI COOL”
cooling terminal on the control board. The fan off setting is fixed at 60
seconds to improve cooling efficiency.

Heating Cycle

When the thermostat switch is set on HEAT and the fan is set on AUTO,
and there is a call for heat, a circuit is completed between terminals R
and W of the thermostat. When the proper amount of combustion air is
being provided, the pressure switch will close, the ignition control pro-
vides a 17-second ignitor warm-up period, the gas valve then opens,
the gas starts to flow, ignition occurs and the flame sensor begins its
sensing function. The blower motor will energize 30 seconds after the
gas valve opens, if a flame is detected. Normal furnace operation will
continue until the thermostat circuit between R and W is opened, which
causes the ignition system and gas valve to de-energize and the burner
flames to be extinguished. The vent motor will operate for 15 seconds
and the blower motor will operate for the amount of time set by the fan-
off delay jumper located on the control board. See Figure 27. The heat-
ing cycle is now complete, and ready for the start of the next heating
cycle.

If the flame is not detected within 7 seconds of the gas valve opening,
the gas valve is shut off and a retry operation begins. Also, if the flame
is lost for 2 seconds during the 10-second stabilization period, the gas
valve is shut off and a retry operation begins. During a retry operation,
the vent motor starts a 15 second inter-purge and the ignitor warm-up
time is extended to 27 seconds. If the flame is established for more than
10 seconds after ignition during a retry, the control will clear the ignition
attempt (retry) counter. If three retries occur during a call for heat, the
furnace will shut down for one hour. If at the end of the one hour shut
down there is a call for heat, the furnace will initiate a normal start cycle.
If the problem has not been corrected the furnace will again lockout
after three retries.

A momentary loss of gas supply, flame blowout, or a faulty flame probe
circuit will result in a disruption in the flame and be sensed within 1.0
seconds. The gas valve will de-energize and the control will begin a
recycle operation. A normal ignition sequence will begin after a 15 sec-
ond inter-purge. If during the five recycles the gas supply does not
return, or the fault condition is not corrected the ignition control will lock-
out for 60 minutes.

During burner operation, a momentary loss of power for 50 milliseconds
or longer will de-energize the gas valve. When the power is restored,
the gas valve will remain de-energized and the ignition sequence will
immediately restart.

Hot Surface Ignition System

TROUBLESHOOTING

The following visual checks should be made before troubleshooting:

1.

Check to see that the power to the furnace and the ignition control
module is ON.

2.

The manual shut-off valves in the gas line to the furnace must be
open.

3.

Make sure all wiring connections are secure.

4.

Review the sequence of operation. Start the system by setting the
thermostat above the room temperature. Observe the system’s
response. Then use the troubleshooting section in this manual to
check the system’s operation.

Main power to the unit must still be interrupted at the main power
disconnect switch before any service or repair work is to be done to
the unit. Do not rely upon the interlock switch as a main power dis-
connect.
Blower and burner must never be operated without the blower
panel in place.

HOT SURFACE IGNITION SYSTEM
Do not attempt to light this furnace by hand (with a match or any
other means). There may be a potential shock hazard from the
components of the hot surface ignition system. The furnace can
only be lit automatically by its hot surface ignition system.

Never bypass any safety control to allow furnace operation. To do
so will allow furnace to operate under potentially hazardous condi-
tions.
Do not try to repair controls. Replace defective controls with UPG
Source 1 Parts.
Never adjust pressure switch to allow furnace operation.

Summary of Contents for GG8S*MP

Page 1: ...Position without filter Bottom Return 24 Blower Performance CFM Any Position without filter Left Side Return 25 These high efficiency compact units employ induced combustion reli able hot surface ign...

Page 2: ...binet support the ends of the furnace rather than lifting by the cabinet flanges at the return air openings bottom or sides or supply air opening 13 When lifting the furnace it is acceptable to use th...

Page 3: ...the National Fire Protection Association Inc Batterymarch Park Quincy MA 02269 or for only the NFGC contact the American Gas Association 400 N Capital N W Washington DC 20001 or www NFPA org CANADA NS...

Page 4: ...noxide detector with an alarm and battery back up is installed on the floor level where the gas equipment is to be installed In addition the installing plumber or gasfitter shall observe that a batter...

Page 5: ...otated down for shipment In order to use the flanges remove the screw holding an individual flange rotate the flange so it is in the upward position and reinstall the screw then repeat this for all 4...

Page 6: ...CE ASSEMBLY PC SERIES COILS These upflow coils are designed for installation on top of upflow fur naces only If the coil is used with a furnace of a different size use a 45 transition to allow proper...

Page 7: ...will be necessary to seal the edges of the bottom panel to the casing using tape or other appropriate gasket material to prevent air leakage BOTTOM RETURN AND ATTIC INSTALLATIONS Bottom return applica...

Page 8: ...one support at the supply end of the furnace one support located approximately in the center of the furnace near the blower shelf and the third support should be at the return end of the fur nace Mai...

Page 9: ...M m3 min Cabinet Size Cabinet Dimensions Inches Approximate Operating Weights A A cm B B cm C C cm Lbs 40 11 7 800 22 7 A 14 1 2 36 8 13 3 8 34 0 10 3 26 2 89 60 17 6 1000 28 3 A 14 1 2 36 8 13 3 8 34...

Page 10: ...this section specify the type of gas approved for this furnace only use those approved gases The instal lation of a drip leg and ground union is required Refer to Figure 15 FIGURE 13 Side Return Cuto...

Page 11: ...ne LP gas must have the LoNOx screens removed prior to installation and operation See propane instructions Table 5 Nominal Manifold Pressure Manifold Pressures in wc Manifold Pressures kpa Altitude fe...

Page 12: ...ct the thermostat wiring from the wiring connections on the thermostat to the terminal board on the ignition module as shown in Figures 17 or 18 Electronic thermostats may require the common wire to b...

Page 13: ...ressor G Fan PP11C70224 THERMOSTAT RH 24 Volt Hot Heat XFMR RC 24 Volt Hot Cool XFMR W Full Stage Heat Clipping Jumper W914 for electric heat on thermostat is not necessary 24VAC Humidifier Optional C...

Page 14: ...S HGD HP RHS O Reversing Valve Energized in Cool C 24 Volt Common R 24 Volt Hot W1 66 out Heat Y Compressor DEMAND DEFROST CONTROL X L Malfunction Light W Auxiliary Heat SINGLE STAGE HEAT PUMP 1 1 Par...

Page 15: ...he furnace that operates on W2 will be supplying cold air in the Heating mode to the occupied spaces unless W2 is energized GAS PIPING Furnace gas supplies must be provided as specified with these ins...

Page 16: ...scribed below 2 Connect a wire from the TWIN terminal of Furnace 1 to the TWIN terminal of Furnace 2 3 Install a separate 24V relay as shown in the diagram below Use of this relay is required as it en...

Page 17: ...ney must extend at least 5 ft 1 5 m above the highest equipment draft hood or flue collar FAN ASSISTED COMBUSTION SYSTEM This appliance is equipped with an integral mechanical means to either draw pro...

Page 18: ...must be given consideration in calculating free area If the free area of a specific louver or grille is not known Refer to Table 7 to estimate free area Ventilated Combustion Air The ventilated attic...

Page 19: ...simply slide the NOx screens out of the heat exchanger tubes and discard the screens 8 Replace all components in reverse order Reconnect all wiring CARBON MONOXIDE POISONING HAZARD Failure to follow t...

Page 20: ...ilots 2 Run furnace for a minimum of 3 minutes in heating operation 3 Measure time in sec for gas meter to complete 1 revolution and note reading The 2 cubic feet dial provides a more accurate mea sur...

Page 21: ...22 164 327 818 64 56 112 281 23 157 313 783 66 54 109 273 24 150 300 750 68 53 106 265 25 144 288 720 70 51 103 257 26 138 277 692 72 50 100 250 27 133 267 667 74 48 97 243 28 129 257 643 76 47 95 23...

Page 22: ...n and follow the operating instructions to place the unit back in operation 3 Adjust manifold pressure by adjusting gas valve regulator screw for the appropriate gas per the following 4 After the mani...

Page 23: ...must be long enough to adequately cool the furnace but not so long that cold air is blown into the heated space The fan off timing may be adjusted by positioning the jumper on two of the four pins as...

Page 24: ...638 2540 2448 2339 2224 2111 1974 1831 Medium High 2234 2233 2147 2092 2042 1974 1907 1820 1705 1575 Medium Low 1722 1716 1690 1681 1603 1553 1489 1426 1335 1241 Low 1396 1375 1348 1325 1263 1200 1150...

Page 25: ...ow 1126 1115 1095 1049 1027 996 957 929 840 742 080C22 High 2972 2863 2769 2671 2571 2465 2352 2227 2095 1950 Medium High 2173 2146 2103 2082 2036 1966 1904 1827 1738 1621 Medium Low 1670 1667 1647 16...

Page 26: ...ion occurs and the flame sensor begins its sensing function The blower motor will energize 30 seconds after the gas valve opens if a flame is detected Normal furnace operation will continue until the...

Page 27: ...ed Flashes description below If the main limit switch opens five times within a single call for heat the control will also indicate 4 Red Flashes and will enter a one hour soft lockout 5 RED FLASHES T...

Page 28: ...ill flash three green flashes when the memory has been cleared then will resume the normal slow green flash after a five second pause SECTION X REPLACEMENT PARTS LIST DESCRIPTION MOTOR MOTOR DIRECT DR...

Page 29: ...lower motor speed connections shown are typical but may vary by model and application LEGENDE DS Commutateur de porte MOT Moteur soufflerie TST Thermostat ROS Commutateur de roulement IDM D induct mot...

Page 30: ...ge without notice Published in U S A 356485 UIM G 1211 Copyright 2011 by Johnson Controls Inc All rights reserved Supersedes 356485 UIM F 0910 Johnson Controls Unitary Products 5005 York Drive Norman...

Reviews: