Section Assembly of Four-Piece Cells (cont’d)

Prior to rigging the coil section, install sealer tape along verti-
cal flange between the coil and plenum sections.  Align the coil 
section to plenum utilizing drift pins in the alignment holes on 
plenum  section,  which  are  accessible  from  outside  the  unit.  
From inside plenum section, accessible once drift eliminators 
are removed, fasten hardware to coil section using pre-installed 
welded nuts on coil section. Secure the coil section to lower 
section using 1/2” hardware.

Figure 9 - Typical Bolting

Section Assembly of Two-Piece Cells

To assemble a two-piece cell, position the lower section on the 
unit supports and bolt in place. Install sealer tape supplied with 
the unit, as illustrated in Figure 7, on the mating flanges of the 
lower section in a continuous line. Sealer tape should overlap 
at each corner. Using drift pins, as shown in Figure 8, in the bolt 
holes provided, guide the top section onto the bottom section 
starting with bolt hole at one corner and following down the 
flange. Screw in place using the self-tapping screws or bolts, 
supplied with the unit, to ensure leak-free operation.

Figure 7 - Assembly of Two-Section Unit.

Figure 8 - Drift Pin Alignment

BLEED LINE INSTALLATION

On ECH units operating with a remote sump tank, install a bleed 
line with valve between the system circulating pump discharge 
riser and a convenient drain. Locate the bleed line in a portion of 
the riser piping that drains when the pump is off. ECH units that 
are furnished with a factory-installed circulating pump include 
a bleed line with valve.

 

CAUTION

The bleed valve should always be open when the unit is in 
operation, unless the bleed rate is automatically controlled 
by a water treatment system. See Bleed Rate section under 
Water Treatment at the end of the MAINTENANCE section.

Optional Accessories and Equipment

All optional accessories such as ladders, safety cages, platforms 
and  handrail  packages  should  be  installed  as  shown  on  the 
appropriate reference drawing in the submittal package from 
Johnson  Controls.  Any  applicable  reference  drawings  are  in-
cluded with the unit in the envelope attached to the side of the 
unit marked “Contractor’s Installation Information.”

Summary of Contents for Frick ECH

Page 1: ...ECH D Evaporative Condensers Please check www jci com frick for the latest version of this publication THIS MANUAL CONTAINS RIGGING ASSEMBLY START UP AND MAINTENANCE INSTRUCTIONS READ THOROUGHLY BEFO...

Page 2: ...if Extended Downtime is a Concern 21 INSTALLATION Rigging and Assembly Instructions ECH ech d Evaporative Condensers 4 Shipping 4 Check Unit Before Rigging 4 Anchoring 4 Rigging 5 Section Assembly of...

Page 3: ...ift Eliminators Spray Water Distribution System Power Train Axial Fan s Single Side Air Inlet ECH Dual Air Inlet ECH D Suction Strainer Spray Riser Pipe Bleed Valve Spray Pump Access Door Spray Pump M...

Page 4: ...pe required to assemble sections or component parts are furnished by Frick and are shipped with the unit A checklist inside the envelope attached to the side of the unit marked Contractor s Installati...

Page 5: ...tance between the spreader bar attachment points Figure 1 Two Section Units Figure 2 Plenum and Coil Sections Figure 3 Lower Section Two Section Units Four Section Units Model Number Section H W1 W2 E...

Page 6: ...ler tape on the edge flange as shown in Figure 5 For multiple cell installations remove tie down plates from plenum and coil sections prior to setting sections Using drift pins in the bolt holes provi...

Page 7: ...ith bolt hole at one corner and following down the flange Screw in place using the self tapping screws or bolts supplied with the unit to ensure leak free operation Figure 7 Assembly of Two Section Un...

Page 8: ...for more details WARNING Do not perform any service on or near the fans motors drives or inside the unit without first ensuring that the fans and the pumps are disconnected and locked out NOTICE 1 Re...

Page 9: ...in strainer and re install Cover the fan discharge opening to keep out dirt and debris Lubricate the fan shaft bearings motor base and motor base adjusting screw Close the shutoff valve in the makeup...

Page 10: ...ambient temperature is below freezing Contact your local Frick Representative for guidelines on the installation of an emergency coil drain system Further protection against coil freeze up is possibl...

Page 11: ...mall portion of the recirculating water to a drain is used to control the concentration of dissolved solids On rare occasions this may be adequate to control scale and corrosion More often however che...

Page 12: ...Start up and Start up Following a Shutdown Period 1 To minimize the risk of biological contamination during a shutdown period of three days or more it is recommended that the entire system evaporativ...

Page 13: ...ingle speed fan motors and drive assemblies One drive assembly is sized for full speed and load and the other is sized for approximately 2 3 speed and consumes only 1 3 the design horsepower The Senti...

Page 14: ...belt deflects be tween 1 4 and 3 8 as shown in Figures 12a and 12b Belt tension adjustment if required 1 Loosen the lock nut on the motor base adjusting screw 2 Turn the motor base adjusting screw cl...

Page 15: ...th the unit idle Add oil if level is below the oil level sight glass The standard oil provided is mineral oil Synthetic lubricants are also available as an option see Table 5 Refer to Table 6 for norm...

Page 16: ...ties Service Oil Citgo Pacemaker 220 Conoco Hydroclear Multipurpose R O Oil 220 Exxon Teresstic 220 GulfOil Harmony 220 MobilOil DTE Oil BB Pennzoil Pennzbell TO 220 Philips Petroleum Magnus 220 Shell...

Page 17: ...nal Start up Purge both bearings with new grease prior to start up 3 Operation Purge bearings every 2 000 hours of operation or once every 3 months whichever occurs first 4 Extended Shutdown Purge bea...

Page 18: ...ent accumulations of scale corrosion sludge or biological growth which could interfere with the electrical circuit The water level is maintained at the recommended operating level regardless of the sy...

Page 19: ...ontrol of the water quality is being maintained Bleed Line Calculations Bleed rate is determined by the fol lowing formula Bleed Rate B E n 1 Where B Bleed Rate GPM E Evaporation Rate GPM Q GPM x R F...

Page 20: ...se adjusting screw X X X Check and lubricate optional gear drive See gear drive section for detailed instructions and schedule Check drive alignment X Check motor voltage and current X X X Clean fan m...

Page 21: ...inventory of commonly used parts Even with this fast delivery capability it is still recommended that certain essential emergency repair parts be maintained in your local inventory to minimize any po...

Page 22: ...ech Evaporative Condensers notes 140 910 IOM DEC 13 Page 22...

Page 23: ...ech Evaporative Condensers notes 140 910 IOM DEC 13 Page 23...

Page 24: ...Page 24 Johnson Controls 100 CV Avenue Waynesboro PA 17268 1206 USA Phone 717 762 2121 FAX 717 762 8624 www jci com frick Form 140 910 IOM 2013 12 Supersedes 140 910 IOM 2009 11 Subject to change with...

Reviews: