45
·
frequency as following.
Step 1: Ensure the system is running and there has water output, enter
to ”StopFreq”
.
Step 2: To reduce the value of “StopFreq”. Reduce by 5Hz each time and
press
"ENTER" to check the system performance. Keep reducing the value till the
water just can not come out. Then adjust the value slightly until the water just
come out, this value is the very data of StopFreq.
10.3.4 Only AC Input, Disconnect DC input
Please refer to
"10.3.1 Only DC Input. "
for commissioning steps.
At the first running, ender user need to long-press "ON / OFF" key for 4 seconds around,
then inverter start to run.
Stop inverter, press "ON / OFF" key (1 second around), inverter shut down.
So far, your solar pumping systems first commissioning is
completed! Thank you for using green energy!
10.4 Commissioning for JNP22KH-V5~JNP55KH-V5
10.4.1 Modify motor parameters
After confirming both of the input and output connection are in correct way,
then switch on DC switch or Connect grid input, then LCD screen will show
information as below.
10.4.2 Only DC Input. Disconnect grid input