Installation & Setup Guide

Connect your device to the PhazrConfig Network.

Open the Measurz Mobile App and sign in with your certified installer credentials.

Click Phazr from the dropdown menu.

Verify you are connected to the PhazrConfig network and hit 

Next.

Scan or type in the 8 digit barcode on the bottom of the Phazr Hub and hit 

Next.

Click the select all button to select all Phazrs. Checkmarks will appear in all the configure and 

Measurz boxes. Once all Phazrs are completed, hit 

Next

 and the process for configuring 

Phazrs to the network and Measurz is finished. 

4.0

 Phazr Configuration

Info:

 The Ubiquiti AmpliFi WiFi router and mesh point system should 

already be installed prior to Phazr commissioning.

Info:

 A WiFi enabled phone or tablet with Measurz Moble app is    

 

 

 

 

 

 

    

required to commission a Phazr system 

8

Summary of Contents for Phazr

Page 1: ...ide The following guide details the steps and procedures to properly install and commission a JLM Phazr system If you require assistance during the installation or commissioning of a Phazr system plea...

Page 2: ...1 1 Roof Type and Mounting System Options 1 2 Mounting Phazr 2 0 Application App Installation 3 0 Phazr Hub and AmpliFi HD Router System Installation 4 0 Phazr Configuration 4 1 Linez Installation 5 0...

Page 3: ...Phazr to the micro inverter are three feet 3 long Be sure that you do not mount the Phazrs and micro inverters or DC power optimizer too far apart WARNING Ensure the DC jumper wires from the Phazr to...

Page 4: ...tween stand offs to avoid excessive twisting of the racking Racking Iron Ridge XR1000 or equivalent Must be mounted as far up on the L Bracket as possible for proper Phazr clearance L Bracket Iron Rid...

Page 5: ...their associated truck cable AC connection prior to mounting Phazr for an easier installation process 1 Mount each Phazr to the mounting rail using two 1 4 micro inverter mounting T bolts Iron Ridge M...

Page 6: ...ounding system using the factory installed grounding lug on the Phazr 3 Unpackage the provided DC jumper cables and plug them into the Phazr DC OUT terminals Plug the other end of the cables into the...

Page 7: ...nto the Phazr DC IN terminals and mount the PV module to the rails DC IN 2 0 Application App Installation 1 Search for JLM Energy in Google Play Android or the App Store Apple and you will find the Me...

Page 8: ...the ethernet cable into one of the available LAN ports on their home router 1 Install Phazr Hub by plugging the provided micro USB cord and ethernet cable into the Amplifi Router Info Make sure to pos...

Page 9: ...m of the Phazr Hub and hit Next Click the select all button to select all Phazrs Checkmarks will appear in all the configure and Measurz boxes Once all Phazrs are completed hit Next and the process fo...

Page 10: ...ted network Once Linez is installed and powered on it will automatically connect to Measurz 5 0 Completing Installation Call into JLM Customer Service Support at 800 475 3960 to verify connectivity to...

Reviews: