Please consult your manual for full information or consult your local dealer.
Control panel – DSE
Stand Alone Manual Operation
Single generator, controlled manually through
its generator controller. Load is monitored by
the operator.
Starting Procedure
Perform all the pre-start checks before starting
the generator.
1.
Turn on the digital controller switch.
2.
Wait for a few seconds, to allow the controller
to power up and the display to stabilise.
3.
Make sure the LED (Light Emitting Diode) is
illuminated on the earth leakage trip and there
is no trip active where required.
4.
Make sure the main power supply MCCB
is switched off.
5.
Check the emergency stop button is fully out,
if necessary twist to reset the button.
6.
Complete all pre-start, system and engine
checks.
7.
Press the start button and the machine will
start in manual.
8.
The engine will run up to speed and stabilise.
9.
Check that the machine operation is correct
using the screen information.
10.
Make sure the ‘power on’ LED is illuminated
on the earth leakage trip and there is no
trip active.
11.
Turn on the main power supply MCCB.
12.
The generator can now be loaded.
13.
If the earth leakage relay trips at this point
consult the site electrical installation engineer.