27.5.3 Greasing
Use
Section
to keep a record of all scheduled servicing. Unless specified otherwise, components
should have one pump of grease after every 16 loads or 50 hours. Use SAE multi-purpose high
temperature grease with extreme pressure (EP) characteristics on all areas requiring grease lubrication.
1. Wipe grease fitting clean before greasing, to avoid injecting dirt and grit.
2. Replace and repair broken fittings immediately.
3. If fittings will not take grease, replace immediately.
When creating a maintenance schedule please keep in mind:
•
Wheel hubs should be greased periodically and repacked yearly. If the mixer is running through
muddy, sandy, dusty or wet conditions greasing intervals should be more frequent.
•
When greasing through the central grease lines be sure to inspect the integrity of the line. If a line
is split, cracked and/or disconnected replace the line immediately.
•
Jaylor mixers are equipped with two driveshaft assemblies. Depending on the options specified,
grease locations will vary. Grease is required at each cross or ‘u’-joint found on the driveshaft.
Crosses will require
1 pump every 16 hours or 50 loads
. See
Figure 31
and
Figure 32
for typical
grease locations.
IMPORTANT:
The service intervals shown are typical. Always follow the instructions supplied with
the PTO Shaft for full service information.
IMPORTANT:
When greasing crosses on the driveshaft, always inspect the condition of the yoke
assemblies. Apply grease to contact areas if required, check connections, and check condition of the
shear bolt if applicable.
Figure 31 - PTO Shaft Grease Locations
1. Standard PTO Shaft
2. Constant Velocity Joint PTO Shaft
Grease one pump after every 8 hours or 25 loads
Grease one pump after every 16 hours or 50 loads