FUEL PIPING
Ø
A supply and return fuel pipe is required in each DG set .
Ø
SDGs upto 750 KVA are provided with fuel tanks inside the acoustic
enclosure.
Ø
Outside fuel tank will be provided as per requirement.
Ø
For fuel tank inside the acoustic enclosure, fuel piping is done by the
manufacturer/supplier.
Ø
However, for Fuel Tank outside the enclosure, fuel piping is to be done
by the customer.
Ø
Size of the fuel piping should be 12mm upto 250 KVA DG set.
Ø
B/C Class M.S. pipe (19 mm - 25mm I.D.) is recommended For fuel
piping above 250 KVA DG sets.
Ø
MS pipe should be used with proper welded joints.
Ø
Stop valve and flange should be used in supply line to engine near fuel
tank (for Fuel Tank mounted outside).
PRECAUTIONS TO BE TAKEN FOR FUEL PIPING AND FUEL SYSTEM.
Ø
Never use GI pipes in fuel piping of DG set.
Ø
Joints should be welded and never threaded.
Ø
Pipe should be above ground level with proper MS support.
Ø
All joints should be tested for any seepage or leakage.
6
JAKSON & CO.
Summary of Contents for JakPower Kirloskar Koel Green EA10 G1
Page 1: ......
Page 2: ......
Page 30: ...26 JAKSON CO BY KIRLOSKAR POWER JAKSON COMPANY 550 13...
Page 31: ...27 JAKSON CO BY KIRLOSKAR POWER JAKSON COMPANY 550 13...
Page 35: ...POWER JAKSON CO...
Page 36: ......