Three-phase photovoltaic grid-connected inverter
Installation
21
Figure 4.4 Side-by-side installation space requirements
(4) The ambient temperature of installation should be -25°C~60°C
(5) The installation site should be away from electronic devices which can generate strong
electromagnetic interference
(6) The inverter should be installed on firm and solid surface eg wall surface and metal
bracket
(7) The installation surface should be vertical to the horizontal line, as shown in Figure 4.5
Install the inverter vertically or backward
≤
15
°
to facilitate heat dissipation.
Do not tilt the inverter forward, horizontal, upside down, over- backward, and roll when install the
inverter.
Fig 4.5 Installation position of the inverter