Procedure for reconditioning an FCPM
Portable Load Unit troubleshooting
Portable Load Unit LED states
Contact Intelligent Energy Product Support
5
7
6
8
For all other issues and questions please contact your local
Intelligent Energy representative or the Product Support team by email
[email protected]
To carry out a reconditioning cycle, after the components have been connected
to the FCPM, as described in Section 4 above, use the following process. It should
be noted that during reconditioning the FCPM will run loudly and periodically go
silent for a few seconds. In addition the PLU status LED will occasionally flash orange
briefly. This is expected and normal behaviour.
· Start up the FCPM in the normal way (long press, then a short press)
(See FCPM manual for full startup procedure)
· Check that the PLU LED is flashing green (the FCPM LED will be flashing green)
· Verify that the FCPM is running
· Allow the FCPM and PLU to operate for 20 minutes (during Reconditioning the
FCPM will run and the fan will be on high)
· Press PLU Stop button to switch off the PLU
· Hold the FCPM button to switch off the FCPM
· Disconnect PLU and RCD from the FCPM
Fault
Cause
Action
Red flash
Over temperature fault
1. Switch unit off
2. Disconnect FCPM from PLU
3. Wait for 10mins to cool down
4. Restart PLU
5. If the fault persists Contact Intelligent Energy
Product Support
Over voltage on
input fault
LED Colour
LED Mode
Status
Green
Flash
Operational, dissipating power
Amber
Flash
Operational, not dissipating power
Red
Flash
Fault
Any colour
Fast flash
Boot loader fault
RCD port
Regulator interface
Micro SD card slot
(supplied)
PLU power
connection
point
FCPM power output
Customer interface
1
2
3
FCPM reconditioning setup process
4
4.1
4.3
4.2
Mechanical setup for reconditioning
The PLU and FCPM should be located on a stable surface for reconditioning. The
Hydrogen source should be secured in accordance with local regulations. There should
be adequate ventilation for operation of the FCPM and cooling air flow of the PLU.
Connection of the Portable Load Unit
The FCPM should be connected from the power out port to the power connection port
on the PLU, using a standard XT60 power cable.
Connection of the Reconditioning Dongle
The Reconditioning Dongle should be connected to the Reconditioning port
1
on the FCPM.
The FCPM will need the hybrid battery and fuel connections as for normal operation.
See FCPM manual.
Note: