PART 2 INSTALLATION INSTRUCTIONS
TRAC 878 TRAYWASHER
INSTALLATION INSTRUCTIONS
These installation instructions are intended for qualified
equipment installers.
PLACEMENT
Carefully uncrate the machine. Take caution not to
damage components which may be mounted on the
top or sides of the machine.
Set the unit in place and adjust the feet to level the
machine.
TABLING
Load and unload tables should be pitched towards the
machine to return excess water into the machine.
Fasten the tables to the load and unload side of the
machine. Most installations require fastening the turn-
down lip of the dish tables to the side of the machine
with flathead countersunk screws.
The table design should provide horizontal clearance
of 30” for servicing. Install rack guides on exit table
using mounting studs provided.
ELECTRICAL CONNECTIONS
Connect electrical lines sized for the correct voltage,
current and phase of the machine. These should
agree with the machine requirements indicated on the
nameplate and labels on the control panel.
Machines not provided with a single-point connection
require two separate electrical connections for:
1.
pumps and control circuit
2.
wash tank heater(s)
If an electrical booster is provided, connect the booster
directly to power source.
CAUTION:
Connections must be made to a circuit breaker or
fused disconnect as provided by the end-user and
required by local codes. A laminated wiring diagram
is inside the control panel.
5
®
TRAC 878 Technical Manual 2018
www.insingermachine.com 800-344-4802
MECHANICAL CONNECTIONS
All lines must be flushed prior to use to remove debris.
Connect a 110°F (for 70°F rise) or a 140°F (for 40°F
rise) water line for tank fills and booster as tagged and
noted on the installation drawings.
If machine is provided with steam heat connect the
steam lines and steam condensate lines as tagged
and noted on installation drawings.
Connect the drain lines. Drain lines must be as speci-
fied on installation drawings.
If a booster is provided, a 110°F (for 70°F rise) or a
140°F (for 40°F rise) water connection is necessary. A
steam booster also requires a condensate line.
CAUTION:
As with any 3 phase system, an electrician must
check all motors for proper phasing, i.e., Pump
motors must be running in direction indicated by
arrow on housing.
CAUTION:
Drain lines must be as specified on installation
drawings. Drain line should be properly vented and
should have fall of not less than 1/4” to the foot of
proper flow.
CAUTION:
Some area plumbing codes require drains to flow
into an open gap with an opening twice the diameter
of the pipe. Check with your local plumbing codes for
the type of drain connection required.
CAUTION:
Do not reduce the size of lines as specified in
installation drawings. All lines are sized to facilitate
necessary flows, pressures, etc.