background image

9

Adjust Clearance

Refer to

Figure 9, p. 17

.

There is an adjustment screw located below reducer
adapter.

1. Loosen capscrews attaching trolley drive to

sideplate.

2. Loosen jam nut and rotate adjustment screw to

achieve clearance.

3. Tighten jam nut and mounting screws.

If a larger adjustment is required.

1. Add shims between rack segment and beam to

decrease distance.

Installing Rack Segments Onto Beam

Refer to

Figure 7, p. 17

and

Figure 8, p. 17

.

Rack segments should be installed on the outside edge
of the lower flange of the trolley beam. Allow 1/4 inch
(6.5 mm) clearance between the edge of the lower
flange and rack segment for fillet weld. The rack
segments should be clamped tight against the lower
flange so that there is no sagging. Sagging of the rack
could cause the drive pinion to bind as it traverses
along the runway beam.

Racks are provided in segments. These segments
should be jack welded (refer to

Figure 8, p. 17

in place

and the trolley traversed the entire length. During this
movement observe for any high or low spots and
correct. Also check each segment connection for drive
tooth contact and correct as necessary. When all
clearances are achieved, weld both sides of the rack to
the beam flange to prevent corrosion between the rack
segment and beam.

Chain Container

When a chain bucket is used, always connect the free
end of the chain to the hoist. Attach the chain container
to the hoist. Run bottom block to the lowest point and
run hoist in the ‘UP‘ direction to feed the chain back
into the container.

W

WA

AR

RN

NIIN

NG

G

• Allow chain to pile naturally in the chain

container. Load chain that does not pile
naturally can chafe excessively, leading
to sparks.

N

NO

OT

TIIC

CE

E

• Make certain to adjust the balance chain

so that the chain container does not
contact the load chain.

Attaching Limit Stop

1. Install limit stop as described under ‘Load Chain

Replacement‘.

2. Run hoist slowly in the both directions to verify

limit stops activate and hoist ceases to operate.

Accu-Trol® Pendant

Refer to

Figure 10, p. 18

.

Check that all hose connections are tight and that hoses
are not twisted or crimped. Refer to Product Manual
MHD56014 for hose connections and all other
operation information.

Pendant lengths up to 66 ft (20 m) are available.
Contact factory for pendant lengths greater than 66 ft
(20 m).

C

CA

AU

UT

TIIO

ON

N

• To avoid damaging pendant hose, make

sure strain relief cable, not pendant
hose, is supporting weight of pendant.

Initial Operating Checks

Hoists are tested for proper operation prior to leaving
factory. Before hoist is placed into service the following
initial operating checks should be performed.

1. After installation of trolley mounted hoists, check to

ensure hoist is centered below trolley.

2. Remove side plate connecting plates.

3. Check for air leaks in supply hose and fittings to

pendant, and from pendant to manifold.

4. When first running hoist or trolley motors a small

amount of light oil should be injected into inlet
connection to allow good lubrication.

5. When first operating hoist and trolley it is

recommended that motors be driven slowly in both
directions for a few minutes.

6. Operate trolley along entire length of beam.

7. Inspect hoist and trolley performance when raising,

moving and lowering test load(s). Hoist and trolley
must operate smoothly and at rated specifications
prior to being placed in service.

8. Check that trolley (if equipped) and hook movement

is in same direction as arrows or information on
pendant control.

9. Raise and lower a light load to check operation of

hoist brake.

10. Check hoist operation by raising and lowering a

load equal to rated capacity of hoist 4 to 6 inches
(100 to 150 mm) off floor.

11. Check operation of limit devices.

12. On trolley units, check ‘O’ ring (360) on breather

plug (362) in trolley drive piston motor has been
removed.

IIn

nsstta

alllla

attiio

on

n

Summary of Contents for Hercu-Link BHS 100

Page 1: ...hese Instructions Edition A May 2018 CCN 47638924 Hercu Link Air B O P Handling Systems Models BHS 50 50 Metric Tons BHS 75 75 Metric Tons BHS 100 100 Metric Tons BHS 150 150 Metric Tons y Product Information ...

Page 2: ... com The use of other than genuine Ingersoll Rand replacement parts may result in safety hazards decreased performance and increased maintenance and will invalidate all warranties Original instructions are in English Other languages are a translation of the original instructions Refer all communications to the nearest Ingersoll Rand Office or Distributor Table 1 Product Information Manuals Publica...

Page 3: ...Onto Beam 9 Chain Container 9 Attaching Limit Stop 9 Accu Trol Pendant 9 Initial Operating Checks 9 Operation 10 Hoist Controls 10 Accu Trol Pendant Operation Push Button Type 10 Emergency Stop 10 Inspection 11 Frequent Inspection 11 Daily Inspection 11 Load Chain Reports 12 Hoists Not in Regular Use 12 Storing the Hoist 12 Lubrication 13 Pivot Points and Bushings 13 Hoist Motor 13 Piston Trolley ...

Page 4: ...sheave s The motor driven brake shaft is connected to brake through a sprag clutch In hoist UP direction clutch allows shaft to rotate without releasing brake No air pressure is applied to brake piston in UP direction The brake shaft cannot rotate in hoist DOWN direction until brake has been released Brake is released by air pressure applied to annular brake piston and piston compresses brake spri...

Page 5: ... testing i e results are as purchased material propertied for those parts M3 Material traceability certificates according to EN 10204 Ex DIN 50049 3 1b on load bearing parts These documents affirm by a department independent of the manufacturing department that the actual parts used in the product are in compliance with the order based on specific inspection and testing i e results are actual mate...

Page 6: ...ceability certificates according to EN 10204 Ex DIN 50049 2 2 on load bearing parts Conformity documents affirm by the manufacturer that parts are in compliance with requirements of the order based on non specific inspection and testing i e results are typical material properties for these parts M2 Material Traceability certificates according to EN 10204 Ex DIN 50049 3 1b on load bearing parts Con...

Page 7: ...air supply lines should be purged with clean moisture free air or nitrogen before connecting to main air inlet Supply lines should be as short and straight as installation conditions will permit Long transmission lines and excessive use of fittings elbows tees globe valves etc cause a reduction in pressure due to restrictions and surface friction in lines Air Line Lubricator Always use an air line...

Page 8: ...n outside of one pair of side plates Install suspension yoke pins 174 and cotter pins 173 on ends of suspension yokes 170 bend ends apart to secure Use lifting lugs on trolley side plates to adequately support hoist and side plates and raise into place on beam flange C CA AU UT TI IO ON N To avoid an unbalanced load which may damage trolley hoist must be centered under trolley using spacers 156 4 ...

Page 9: ...stall limit stop as described under Load Chain Replacement 2 Run hoist slowly in the both directions to verify limit stops activate and hoist ceases to operate Accu Trol Pendant Refer to Figure 10 p 18 Check that all hose connections are tight and that hoses are not twisted or crimped Refer to Product Manual MHD56014 for hose connections and all other operation information Pendant lengths up to 66...

Page 10: ...ng loads and should have a good attitude regarding safety It is the operator s responsibility to refuse to operate hoist under unsafe conditions Hoist Controls Accu Trol Pendant Operation Push Button Type The pendant is a remote control that allows the operator to control the positioning of a load The Accu Trol Pendant is available with 4 or 6 buttons Refer to Accu Trol Pendant manual form number ...

Page 11: ...age or evidence of malfunction such as abnormal noises 1 Lubricator Adjust air line lubricator drops during hoist operation refer to LUBRICATION p 13 section for requirements 2 Surrounding Area Visually check hoist for oil leaks Do not operate hoist if leaking oil is found Ensure surrounding area has no slippery surfaces and is obstruction free 3 Hoses and Fittings Visually inspect for damage air ...

Page 12: ...e maintained documenting condition of load chain removed from service as part of a long range chain inspection program Accurate records will establish a relationship between visual observations noted during Frequent Inspection p 11 and actual condition of load chain as determined by Periodic Inspections Refer to Product Maintenance Information Manual for chain specifications Hoists Not in Regular ...

Page 13: ...synthetics or detergents Table 4 Hoist Motor Recommended Oil Ambient Temperature Recommended Oil Type Below 32 F 0 C ISO VG 32 10W SAE 30 to 80 F 0 to 26 C ISO VG 68 20W SAE a Above 80 F 26 C ISO VG 100 30W SAE Table 4 Hoist Motor Recommended Oil continued a Hoists are shipped from factory with ISO VG 68 20W SAE oil Piston Trolley Drive Motor The motor is splash lubricated by oil in motor housing ...

Page 14: ...ency replace oil in reduction housing once every year To ensure correct performance highest efficiency and long life it is essential that lubricating oil be maintained at correct level Oil capacity for reduction gear assembly is 1 1 gals 4 2 ltr C CA AU UT TI IO ON N Do not over fill Excess oil will reduce operating efficiency and increase oil temperature Use only high quality lubricants in reduct...

Page 15: ...hics Figure 1 MHP4244 Air Supply Filter Separator Lubricator 1 1 Accu Trol Off On Hoist Up Trolley Right Trolley Left Hoist Down 5 3 2 1 4 6 Brake Hoist Motor Trolley Motor Spring Set Release down only Brake Exhaust Limit Paddle ...

Page 16: ...Level Plug Trolley Motor Vented Oil Fill Plug Hook Latch Pivot Hoist Motor Oil Level Plug Hoist Motor Level Plug Located Below Manifold Load Chain Hoist Motor Oil Fill Plug A B C R N P M D E F G H J K L Figure 3 MHP0340 A B C D E Trolley Wheel Flange Side Roller Beam Spacers Ensure Hoist is Centered Beneath Trolley Figure 4 MHP0191 Air Out Regulator Lubricator Air In Filter A B C D E P Pr ro od du...

Page 17: ...sembly Mounted This Side Fillet Weld Allow 1 4 inch 6 5 mm clearance between edge of lower flange and rack segment Apply weld to both sides of rack segment B C D Figure 8 MHP3016 B C D 6 inches 152 mm 6 inches 152 mm Stagger welds along rack A Not to scale Use rack guide for correct track positioning Check clearance between racks 0 08 2 mm Figure 9 MHP1605 A Normal trolley drive mounded above supp...

Page 18: ...ted Fill Plug Oil Level Plug Disc Brake Level Plug Drain Plugs Located at Bottom A C B D Figure 12 MHP0040 A Throat Width Figure 13 MHP0111 max Twisted DO NOT USE Normal Can be Used Figure 14 MHP0102 A B C Diameter Welded Area Wear in These Area P Pr ro od du uc ct t I In nf fo or rm ma at ti io on n G Gr ra ap ph hi ic cs s ...

Page 19: ... work shall be completed by an Ingersoll Rand trained service technician or a Qualified Person a Components 1 year 2 years 3 years 4 years 5 years Inspect Hoist Motor X Inspect Hoist Gearbox X Inspect Hoist Control Valve X Inspect Disc Brake X Inspect Chain X X X X X Inspect Chain Stopper X X X X X Inspect Shut Off Valve X X X X X Inspect Hook or Clevis X X X X X Inspect Hoist Frame X Inspect Hois...

Page 20: ...ildings transport and protect food and perishables and increase industrial productivity and efficiency We are a global business committed to a world of sustainable progress and enduring results ingersollrand com Ingersoll Rand has a policy of continuous product and product data improvements and reserves the right to change design and specifications without notice We are committed to using environm...

Reviews: