Step 1: Take out Storion- SMILE-B3 from the packaging box, as shown in Figure 2.2

. 

Figure 2.3 Stand Positioning 

Step 2: first use the percussion drill (M10 drill) to drill holes in the wall with depth 65mm, then 
install  and  place  the  stand.(1. Insert  the  expansion  pipe  into the  drilled  hole.  Then  pass  the 
tapping screw through the spacer and tighten it with the cross screwdriver), as shown in Figure 
2.3.

 

Figure 2.4 Box Fixation 

Step 3: install the box of Storion-SMILE-B3 (hold the two handles on the back of B3 and install 
the B3 box to the stand), as shown in Figure 2.4. 

Summary of Contents for Storion-SMILE-B3

Page 1: ...V02 Installation Operation Manual Energy Storage System ESS Storion SMILE B3 ...

Page 2: ......

Page 3: ... IMPRINT IINNO Energy Ltd Tel 372 712 3010 E mail sales iinno energy com Web www iinno energy com Add Tammsaare tee 47 Tallinn 11316 Estonia Dec 16th 2018 ___________________________________________________________________ ...

Page 4: ...gy and all rights are reserved Please keep the manual properly and operate strictly according to all safety and operation instructions in this manual Do not operate the system without reading the manual Version Information Version Date Contents V01 Nov 30th 2018 Newly compiled manual V02 Dec 5th 2018 Modify the connection diagram of meters Add the notice of external connection of backup and grid n...

Page 5: ...g Equipment 6 1 2 6 Moisture Protection 7 1 2 7 Operation After Power Failure 7 1 2 8 Battery Safety Datasheet 7 1 3 General Precautions 7 1 4 Parts List 9 1 5 System Appearance 9 1 6 Limitation of Liability 12 2 System Installation 13 2 1 Installation Site and Environment 13 2 1 1 General 13 2 1 2 Restricted Locations 13 2 1 3 Barrier to habitable rooms 14 2 1 4 Installation Tools 15 2 1 5 Instal...

Page 6: ...________________________ Page IV of 29 Contents 4 Routine Maintenance 27 4 1 Maintenance Plan 27 4 1 1 Operating Environment 27 4 1 2 Equipment Cleaning 27 4 1 3 Cable Terminal and Equipment Inspection 27 4 2 Notes 27 5 Annex 28 5 1 Datasheet 28 ...

Page 7: ...ble safe and reliable The schematic is as shown in Figure 1 1 Figure 1 1 Storion SMILE B3 System Figure NOTE For the AC coupled system if only installing Grid CT the system cannot display PV Inverter generated power electric energy production etc 1 2 Safety Introduction 1 2 1 Manual keeping This manual contains important information about operating the system Before operating please read it very c...

Page 8: ...of hot surface Refer to the operating instructions SMILE B3 will be touchable or operable after minimum 5 minutes of being turned off or totally disconnected in case of any electrical shock or injury CE mark VDE mark G59 mark 1 2 4 Setting of Warning Sign for Safety While instructing maintaining and repairing in case of preventing unrelated personnel nearby to cause incorrect operation or accident...

Page 9: ...I sub section 38 3 For the battery cell chemical materials are stored in a hermetically sealed metal case designed to withstand temperatures and pressures encountered during normal use As a result during normal use there is no physical danger of ignition or explosion and chemical danger of hazardous materials leakage However if exposed to a fire added mechanical shocks decomposed added electric st...

Page 10: ... system e g due to casing damage please do not install or operate the system When the system has connected the extended battery module please do not move the system Use strapping if necessary during transportation to prevent tipping Storion SMILE B3 transport must be conducted by the manufacturer or professionals these operations should be recorded and used Certified ABC extinguishers with minimum...

Page 11: ... completeness IINNO Energy provides a complete set of system for on site customers including Table 1 Parts List Storion SMILE B3 8 x M8 60 8 x M6 gasket 1 x installing support 8 x white plug 2 x CT 100A 3000 1 1x installation manual 4 x M4 12 screws 1 x WiFi module optional 1 5 System Appearance Figure 1 2 Storion SMILE B3 External View 1 2 3 ...

Page 12: ...ndby or self inspection Extinguishing out of order fault Extinguishing fault free Normally on out of order com Normally on Normal network connection Flicker connecting to the server Extinguishing un connected network Table 3 SMILE B3 Battery LED Display LED Outer Ring Light Flicker Status SOC Status Description Standby green light flicker 1s work green light flicker 10s SOC 5 5 SOC 25 25 SOC 50 50...

Page 13: ... B3 Left View Table 4 Ports Definition Name Description BMS Additional battery BMS communicate cable connect DRMs DRED connect port only for AU CT1 PV CT communicate cable CT2 Grid CT communication cable BAT Additional battery power positive cable connect BAT Additional battery power negative cable connect BACKUP Critical load connect 80A battery DC Isolator ...

Page 14: ...tem design and installation fail to meet the standards and other relevant requirements Fail to observe local safety regulations Transportation damage including paint scratches caused by friction in packaging during transportation Once the container package is unloaded and the damage is confirmed claims shall be put forward directly to the transport or insurance company Fail to comply with any all ...

Page 15: ...ccess to the SMILE B3 for installation and maintenance purposes The following location are not allowed for installation habitable rooms in ceiling spaces wall cavities on roofs not specifically deemed suitable areas of access egress under stairways under access walkways sites where the freezing point is reached like garages carports or other places sites with humidity and condensation over 85 site...

Page 16: ...abitable room on the other side the wall or structure shall be a suitably non combustible barrier If the mounting surface itself is not made of a suitably non combustible material a non combustible barrier may be placed between the SMILE B3 and the surface of a wall or structure Where the SMILE B3 is located on or within 300mm of the wall or structure separating it from the habitable room the barr...

Page 17: ...er Set Percussion Drilling NOTE Use properly insulated tools to prevent accidental electric shock or short circuits If insulated tools are not available cover the entire exposed metal surfaces of the available tools except their tips with electrical tape Safety Gear It is recommended to wear the following safety gear when dealing with the battery pack 2 1 5 Installation Steps Figure 2 2 Open Stori...

Page 18: ...e percussion drill M10 drill to drill holes in the wall with depth 65mm then install and place the stand 1 Insert the expansion pipe into the drilled hole Then pass the tapping screw through the spacer and tighten it with the cross screwdriver as shown in Figure 2 3 Figure 2 4 Box Fixation Step 3 install the box of Storion SMILE B3 hold the two handles on the back of B3 and install the B3 box to t...

Page 19: ...ng wire harness on the back of the upper cover plate remove the B3 upper cover plate to prepare wiring as shown in Figure 2 5 Note the internal 63A and the external 80A switch must be switched off to prevent short circuit Figure 2 6 Earthing Bonding Position Step 5 the earthing bonding position for Storion SMILE B3 is as shown in Figure 2 6 please use the M4 12 screw In any case the first step aft...

Page 20: ...in Figure 2 7 Note in Australia the neutral of backup and grid circuit should be externally connected on the neutral bar The suggested torque for the waterproof contact is 3 75 N m 10 Figure 2 8 CT Wire Harness Wiring Step 7 Complete for installing CT as shown in Figure 2 8 Note CT communication wires can be connected directly through the silica gel ring of the M20 waterproof contact no need to ma...

Page 21: ...ote The ethernet communication cable can be connected wiring directly through the silica gel ring of the M20 waterproof contact no need to make the on site network cable Figure 2 10 Install WiFi Module Note If using WiFi module open the cover plate of the side WiFi module insert the WiFi module into the terminal port and then fix it with screws as shown in Figure 2 10 Step 9 before re covering the...

Page 22: ...s from BMS shall be connected to the back below part Please pay attention to the positive and negative pole of the button switch wires The suggested torque is 2 6 N m 10 For capacity expansion please refer to the accessory package attached for details 2 1 6 Electricity Meter Wiring The power meter should be installed and connected in the distribution box There are four types of power meters availa...

Page 23: ... 21 of 29 System Installation 2 4 4 2 Electricity meter SM60A if optional SM60A connection with meterplug Figure 2 13 SM60A Connection with meterplug SM60A connection without meterplug Figure 2 14 SM60A Connection without meterplug Note terminal 5 6 connecting RJ45 PIN 3 6 ...

Page 24: ..._________________ Page 22 of 29 System Installation 2 4 4 3 Electricity Meter ADL 3000 if optional ADL 3000 connection without CT without Meterplug Figure 2 15 ADL 3000 connection without CT without meterplug Note terminal 7 8 connecting RJ 45 PIN 3 6 ...

Page 25: ... of 29 System Installation ADL 3000 connection without CT with Meterplug Figure 2 16 ADL 3000 connection without CT with meterplug ADL 3000 connection with CT without Meterplug Figure 2 17 ADL 3000 Connection with CT without meterplug ADL 3000 Connection with CT and Meterplug ...

Page 26: ..._____________________________ Page 24 of 29 System Installation Figure 2 18 ADL 3000 Connection with CT and meterplug 2 4 4 4 Electricity meter ACR10R if optional Figure 2 19 ACR10R Connection Note please pay attention to the CTs direction ...

Page 27: ... LED lights Step 4 Turn on the 80A battery switch of B3 system Step 5 If backup load is applied turn on the external backup AC breaker if not then keep it off 3 2 Switch off Step 1 If backup load is applied turn off the external backup AC breaker Step 2 Turn off the 80A battery switch of B3 system Step 3 Press the button on the battery until the battery LED off Step 4 Turn off the external grid AC...

Page 28: ...with soap and water and seek medical attention Ingestion Induce vomiting and seek medical attention 3 3 3 Fire If a fire breaks out in the place where the battery pack is installed perform the following countermeasures Fire extinguishing media Respirator is not required during normal operations Use Novec 1230 FM 200 or dioxide extinguisher for battery fire Use an ABC fire extinguisher if the fire ...

Page 29: ...has fallen off Check if the cable terminal screws are loose and the terminal position has any signs of overheating Check whether the management system of the system equipment monitor ing system and other related equipment are invalid or damaged Check that the grounding of the equipment is good and the grounding re sistance is less than 10 ohms 4 2 Notes After the equipment are out of operation the...

Page 30: ...onth 0 35 Relative humidity 15 85 Max Operating Altitude 3000m Warranty 5 Year Product Warranty 10 Year Performance Warranty External enclosure s Material SPCC Material Thickness mm 1 0 Inverter Max Grid Backup Current 13 1 Aa c Max Grid Backup Voltage 230 Va c Battery Voltage Range 40 58 Vd c Grid Voltage Range 180 Va c 270 Va c Rated Grid Backup Frequency 50 60 Hz Phase Single phase Power Factor...

Page 31: ... Lithium iron phosphate Battery Rated Voltage 51 2 Vd c Number of cells 16 1P16S Cycle Life 10 000 Standard Charging Discharging Current 56 Ad c 1C Max Charging Discharging Current 60 Ad c External Battery Expansion 1 5 M4856 P in parallel Battery Short circuit Current 200 A Safety IEC62619 Transportation UN38 3 When the temperature is below 0 C or above 40 C the performance will be limited Under ...