35
INSTALLATION
Ideal Logic Heat -
Installation and Servicing
Warning.
Whilst effecting the required gas tightness test and purging air from the gas installation,
open all windows and doors, extinguish naked lights and do noT smoke.
a. Electrical Installation
1.
Checks to ensure electrical safety should be carried out by a
competent person.
2.
ALWAyS carry out the preliminary electrical system checks,
i.e. earth continuity, polarity, resistance to earth and short
circuit, using a suitable test meter.
3.
After wiring the boiler, all grommets in the bottom panel
MUST be in place to ensure that the boiler case sealing is
maintained.
B. gas Installation
1.
The whole of the gas installation, including the meter,
should be inspected and tested for tightness and purged in
accordance with the recommendations of BS. 6891.
In IE refer to IS.813:2002.
2.
Purge air from the gas installation by the approved methods
only.
39 COMMIssIONINg aND TEsTINg
gENERaL
please note
: The combustion for this appliance has
been checked, adjusted and preset at the factory for
operation on the gas type defined on the appliance
data plate.
DO NOT
adjust the air/gas ratio valve.
Having checked:
-
That the boiler has been installed in accordance
with these instructions.
- The integrity of the flue system and the flue seals,
as described in the Flue Installation section.
Proceed to put the boiler into operation as follows:
ChECK ThE OpERaTIONaL (WORKINg) gas
INLET pREssURE
Set up the boiler to operate at
maximum rate.
With the boiler operating in the
maximum rate condition check
that the operational (working) gas
pressure at the inlet gas pressure test
point complies with the requirements -
refer to “Gas Supply” on page 8.
Ensure that this inlet pressure can be
obtained with all other gas appliances
in the property working.
205862-10123
Gas
Supply
Gas Pressure
Test Point
aTTENTION !
IT Is a CONDITION OF ThE MaNUFaCTURERs WaRRaNTy ThaT ThE
BENChMaRK COMMIssIONINg ChECKLIsT Is FULLy COMpLETED
aND LEFT WITh ThE appLIaNCE
As part of the commissioning process, the combustion of this appliance must be checked
and the Benchmark Checklist completed. A flow chart to assist is provided on page 63.
IN
s
T
a
LL
a
TION
Summary of Contents for Logic HEAT 12
Page 2: ...2 Ideal Logic Heat Installation and Servicing...
Page 51: ...51 SERVICING Ideal Logic Heat Installation and Servicing...
Page 58: ...58 SPARE parts Ideal Logic Heat Installation and Servicing...
Page 64: ...64 Notes Ideal Logic Heat Installation and Servicing...
Page 65: ...65 Notes Ideal Logic Heat Installation and Servicing...