Chapter 3
Structured Cable Field Calibration and Testing
3-2
Step 3
¾
Re-insert the tagged end of the first patchcord into the RH unit adapter.
¾
From the DH Field Calibration screen, select START or press AUTOTEST to
begin the third calibration step.
Step 4
¾
From the RH, press AUTOTEST to begin the fourth calibration step.
¾
If calibration is successful, the DH will briefly Display “Calibration Complete” and
the RH will briefly display the PASS light.
¾
If calibration is unsuccessful, the DH will briefly display either a Warning screen
displaying “No Remote Handset” or a Calibration Failure screen.
FIELD CALIBRATION - GG45
This field calibration is a 4-step process. Steps 1 and 2 are performed with the GG45
Calibration Adapters connected to the handsets. Steps 3 and 4 are performed with the
GG45 Permanent Link Adapters open-ended patchcords and then the GG45 Calibration
Load Terminator attached.
The GG45 test kit comprises a Category 6/7 connector product that is backward
compatible with Category 6 - RJ45s.
www.vemco.pl