Use
29
3
Use
PRELIMINARY CHECKS
m
IMPORTANT
–
Before starting the steam generator, it is advisable to perform "
Alkaline boiling
" with subsequent passivation, to remove
any processing residues. Considering the high risk deriving from incorrect chemical treatments, the operations must be
carried out by
professionally qualified personnel
.
–
Before start-up, open the door and insert the turbulators completely inside the front ends of the smoke pipes, taking
care to push them inside by at least 100 mm.
–
Check that all connections are fully tightened
–
Check that the feed water pipe is clean, repeatedly washing it before final filling
–
Close the drain valve, steam inlet and level indicator discharge
–
Open the level and supply shut-off valves (upstream and downstream of the water pump)
–
Check that the door closes properly
–
Verify the presence and condition of all control and safety accessories supplied with the generator.
COMMISSIONING
To start the steam generator:
–
place the main switch at "
ON
" and electrically power the control panel
–
electrically power the pump, briefly activating the selector, and check that:
-
the rotor rotates freely
-
the rotation direction should be correct (indicated in the rear side of the motor)
–
place the pump selector at "
AUT
" and check that there is no consent to start the burner before the water has reached the
minimum level
–
check that the pump stops when the water reaches the maximum level visible in the glass indicator
–
press, for at least 10 seconds, the reset button of the water safety level to activate the delayed type conductivity relay
–
open the generator drain and check on the level indicator at which point the probe intervenes to start the pump
–
position the pump selector at "
0
" leaving the generator drain open and check the level of intervention of the safety probes
with reference to the minimum level plate
–
close the generator drain and position the pump selector at "
AUT
"
–
electrically power the burner, pressurise the generator and adjust the pressure value.
a
ATTENTION
–
On the boilers equipped with manhole, during the first start-up, it is essential to progressively tighten the two nuts (1) of
the hatch while pressure increases. Otherwise, the installation area may become dangerous for the operators in charge,
due to steam seeping through and deteriorating gasket (2) rapidly.
–
Check the intervention of all safety and adjustment accessories described in the relevant chapter.