Figure 48. Upper and lower cable-management arms
As Figure 49 on page 52 shows, the support rail connectors of each CMA assembly are installed on the
rail hooks at the end of the support rails.
Figure 49. Upper and lower cable-management arms
Procedure
1. Remove the loop straps from the upper and lower CMA assemblies. The straps are used only for
shipping.
Installing the upper CMA assembly
Figure 50 on page 53 shows the connectors on the upper CMA assembly.
52 Storwize V5100 : Quick Installation Guide for MTM 2078-424, 2078-12F, 2078-24F, 2078-92F, and 2078-