INSTALLATION INSTRUCTIONS
INSTALLATION SPECIFICATIONS
The AQUA-LAB chemical delivery system has been designed for a fast and hassle free installation. It
comes fully assembled with all of the components pre-wired and plumbed, leaving only the setting of
equipment, and connection of the incoming and outgoing hoses and wires. As follows are the installation
specifications for the AQUA-LAB:
GENERAL:
•
People Required: 2 people
•
Mechanical Skill Level: Basic - Mounting equipment
•
Electrical Skill Level: Advanced - Three phase power and knowledge of local codes is required
•
Pneumatic Skill Level: Basic- pneumatic utility connection required
•
Fluid Skill Level: Basic - Water utility connection required
•
Chemical Knowledge: Advanced - Chemical titrations required
TOOLS AND EQUIPMENT NEEDED:
•
Unpacking: Normal hand tools
•
Assembly: Normal hand tools
•
Wiring: Normal electrical wiring tools
•
Startup: Electrical meter helpful but not required
ESTIMATED TIMELINE:
•
Unpacking: 15 – 30 minutes
•
Frame Mounting: 0.5 – 2.0 hours
•
Fluid Connections: 0.5 – 2.0 hours
•
Motor & Valve Wiring: 1 – 4.0 hours
•
Startup & adjustment: 1.5 – 6.0 hours
UNPACKING
The AQUA-LAB is shipped in a wooden crate for the purpose of protection. Before unpacking, be sure
that the AQUA-LAB is on a level-flat surface. To unpack, perform these steps:
1.
Open the crate using a drill with Phillips bit or Phillips head screwdriver
2.
Cut the cellophane off of the AQUA-LAB by using a utility knife. Be sure to cut either at the
corners or in an area where the knife will not damage the AQUA-LAB.
3.
Using an adjustable wrench, un-bolt the AQUA-LAB from the pallet.
4.
Lift the AQUA-LAB from the pallet. Use assistance if necessary.
5. Dispose of pallet, cellophane and additional packaging materials.