( ) Carefully recheck the 80 3/8" measurements from the center of the Driven
Element bracket to the center of the Director Element bracket. Make certain the
Director Element lies in the same plane as the other elements, then tighten the
anchor securely.
( ) Assemble a 1 ¼” compression clamp and slip it over the. D-1 section. Select the
D-2 section (1
1/8"
x 52 ½”). Slip the unswaged end of the D-2 into the D-1 section
and measure the dimension shown in Figure 3 for your mode of transmission.
Tighten the compression clamps slightly.
( ) Assemble a 1” compression clamp and slip it over the swaged end of D-2. Select
a 10-meter trap and slip the unswaged end into the D-2: Measure the dimension
shown in Figure 3 for your mode of transmission. Make certain the trap drain holes
are facing downward and tighten the compression clamp slightly.
( ) Assemble a 11 /16" compression clamp and slip it over the swaged end of the 10-
meter trap.
( ) Select the D-3 section (7/16" x 17 ¼”) and slip it into the swaged end of the 10-
meter trap. Measure the dimension shown on Figure 3 for your mode of transmission,
then tighten the compression clamp slightly.
( ) Carefully recheck all measurements as shown in Figure 3 and make certain the
trap drain holes are facing downward. Tighten all compression clamps securely.