NOTE:
Verify all electrical termination
during commissioning. It is a
requirement to check all electrical
connections for tightness, where
appropriate all electrical connections
must be re-tensioned prior to powering
up the cabinet.
For all case cleaning activities cabinet should be
turned off. (Electrical power safely disconnected
and refrigeration switched off). Once all cleaning is
completed, remember to turn it back on safely.
• Remove the PVC protective coating on stainless
steel, where applicable
• Remove any residue, silicon or tape marks with a
cloth moistened with rubbing alcohol
• Remove all debris from in and around the case
• Wipe case with a clean, damp cloth, if necessary
Doors:
»
At temperatures above 0°C hand wash with warm
water and using a mild detergent is recommended.
»
A glass cleaner can be used (Windex) using a towel.
(paper towel not suggested).
»
Take care with cleaning, and avoid any materials
that may mark the door (Including fingerprints).
»
Do not use tape, glue, stickers, attachments, magic
markers, or the like on the glass.
»
Do not use razor blades or any other mechanical
device to remove foreign residue or objects directly
from the glass.
»
Do not use abrasive cleaners or materials on the
glass like, Ajax, Scotch Brite or Steel Wool.
»
Do not use cleaners or materials on the glass that
hinder the anti-fog performance (if applicable),
by leaving a residue or damaging the surface.
Examples of these cleaners include : Armor All,
TIlex, Bleach, Windex No-Drip, Windex Wipes,
Pledge or any product containing silicone oils or
waxes.
»
Recommended cleaners include: Greased
Lightning, Formula 409 Grease & Grim, Formula
409 Grease & Surface, Fantastic, Windex Vinegar,
Windex original, Now, Mean Green or Mr. Clean
(degreasing cleaners).
• Check supply power is ready and correct voltage.
(by Licensed Person)
• Confirm correct operation of RCD (if fitted) (by
Licensed Person)
• Ensure that the drain trap is installed the right way
up (
refer to figure 3AC:
drain trap orientation in the
section installing the waste drain)
• Check that all fans and lights (and light RCDs, if
installed) are working correctly.
• Check the anti sweat circuit is working correctly.
• Set expansion valves and EPRs as per Product
Engineering Data – Available from Hussmann.
• Approximately 24 hours after start-up, check that
the case is at correct operating temperature (refer
the Product Engineering Data).
4.1 COMMISSIONING
START UP & CHECKS
TURN POWER ON
CLEANING
CLEANING & MAINTENANCE
Summary of Contents for MPD116
Page 45: ......