INSTALLATION MANUAL
MASTERLINE Ultimate Power
Page 3 of 11
HUBER+SUHNER disclaims any liability resulting from incorrect installation and use, including any damages resulting from the use of tools and
accessories other than the ones recommended herein. Any installation performed by unqualified personnel voids the product warranty provided by
HUBER+SUHNER. All due care and attention must be exercised when performing the installation of these products. For advice concerning the
general handling of these products please contact HUBER+SUHNER.
Step 3
Mount the cable spool onto suitable de-reeling equipment.
Start unwinding from the side where the MLUP connector head
is located. Do not pull on the side where the pulling tube is
attached. Make sure that the spool can rotate freely when
unspooling.
Do not remove the protective bubble foil until immediately be-
fore attaching the MLUP connector head to the mounting
bracket.
Step 4
Use a rope to pull up the cable system.
Check the maximum pulling force (at 50°C
ambient temperature for 1 hour) as specified
on the label attached to the hoisting grip. Do
not apply higher force! The maximum pulling
force equates to the weight of 100 m of cable.
The cable weight is specified on the data sheet. Cabling sys-
tems longer than 100 m may not be lifted more than 100 m
vertically unless a second hoisting grip is used.
Contact HUBER+SUHNER for further installation instructions.
Lead the rope along the left side of the MLUP connector head
down onto the cable hoist and secure it.
Use two tapes to fix the rope to the lower and upper end of the
connector head.
Do not remove the air bubble bag which protects the connector
head while lifting the cabling system.
Pull the cabling system up the mast.
Make sure that the MLUP connector head does not impact
against any structures and is not bent over edges.
Note: 950 N / 95 kg is only an example and
depends on the power cable used