INSTALLATION MANUAL
Page 5 of 15
HUBER+SUHNER disclaims any liability resulting from incorrect installation and use, including any damages resulting from the use of tools and
accessories other than the ones recommended herein. Any installation performed by unqualified personnel voids the product warranty provided by
HUBER+SUHNER. All due care and attention must be exercised when performing the installation of these products. For advice concerning the
general handling of these products please contact HUBER+SUHNER.
Step 9
Fix the power and fiber optic breakouts with suitable
HUBER+SUHNER cable clamps. Depending on the number of
breakouts and if power breakout cables are connectorised or
not, different cable clamps are needed. Contact H+S sales office
or see the cable clamp portfolio
http://www.hubersuhner.com/en/products/fiber-optics to select
the right cable clamps.
The first clamps has to be applied 0.5m above the housing. The
cable has to be fixed straight and in line with the MLEH
enclosure. Do not bend breakout cable direct after the housing
exit and avoid side load on the housing exit.
Do not over bend the cables. Minimum bend
radius for power cable and fiber optic cable is 10
cm. Avoid side load on the power and fiber optic
connector.
All connectors (fiber optic and power) are protected using
waterproof (IP67) protection caps.
Step 10
All connectors on the breakout cables are protected with water
proof (IP67) protection caps.
Do not remove the cap if no jumper cable is
connected. When removing the cap instently mate
the plug connector to avoid dirt entering the
connector.