Install the VCN520/VCN540 in the cabinet. Carry the device to install from both sides. Slowly move
it to the front of the cabinet.Lift the subrack to a position higher than the slide rail . Gently place the
subrack on the slide rail and push it into the cabinet along the slide rail, as shown in the lower-left
figure. Keep pushing the subrack until the mounting ears of the subrack are close to the mounting
bar at the front of the cabinet.
7
8
Connect the M6 screws (prepared by users) through the holes of the mounting ears. Use a Phillips
screwdriver to tighten the M6 screws on the mounting ears. Use two M6 screws to configure each
mounting ear. Separately secure the mounting ears on both sides of the subrack on the mounting
bar at the front of the cabinet, as shown in the lower-right figure.
7
5.3.2 Multi-Device Deployment Scenario
Note
When multiple VCN520s or VCN540s are deployed, a guide rail needs to be installed for each device.
A VCN520 or VCN540 requires 2 U space. A guide rail requires 1 U space. Therefore, installing a
single device requires a total of 3 U space. Before installing devices, properly plan the cabinet space.
For details about how to install a device in the cabinet, see the single-device deployment scenario.
This section introduces how to install multiple devices in the cabinet.
If multiple VCN520s or VCN540s are installed, a guide rail needs to be installed for each device, as
shown in the following figure.