4.
Install a floating nut to the other front mounting bar in the same way.
Step 2
Install the L-shaped guide rails.
1.
Position a guide rail horizontally in contact with the mounting bars in the cabinet.
2.
Tighten the screws to secure the guide rail. See
.
Figure 4-4
Installing an L-shaped guide rail
3.
Install the other guide rail in the same way.
Step 3
Install the server.
1.
Lift the server. This task requires at least two people.
2.
Place the server on the guide rails and slide it into the cabinet. See (1) in
.
2288H V5 Server
User Guide
4 Setup
Issue 04 (2018-09-04)
Copyright © Huawei Technologies Co., Ltd.
71