4
Setup
4.1 Environmental Requirements
4.4 Installing the Server on Guide Rails
4.5 Connecting External Cables
4.1 Environmental Requirements
NOTE
For details about the safety precautions to be observed when you install or replace servers and their
parts, see the
4.1.1 Space and Airflow Requirements
To allow for servicing and adequate airflow, observe the following space and airflow
requirements:
l
Install the server in an access-restricted area.
l
Keep the area in which the server is located clean and tidy.
l
To facilitate heat dissipation and maintenance, keep a clearance of 800 mm (31.50 in.)
between walls and the front and rear doors of the cabinet.
l
Do not block the air intake vents. Otherwise, air intaking and heat dissipation will be
affected.
l
The air conditioning system in the equipment room provides enough wind to ensure
proper heat dissipation of all components.
The server draws in cool air from the front of the cabinet and exhausts hot air from the rear.
Therefore, the front and rear of the cabinet must be well ventilated for optimal heat
dissipation.
shows the direction of heat dissipation.
2288H V5 Server
User Guide
4 Setup
Issue 04 (2018-09-04)
Copyright © Huawei Technologies Co., Ltd.
67